Dryden Facilities Support Center walls going up

NASA photograph by Tony Landis
The concrete-block masonry walls of NASA Dryden's new Facilities Support Center are rising as captured in this photo taken May 23 from the top of Dryden's main building.

Following completion of underground infrastructure and installation of a retaining wall in recent weeks, masons began erecting the concrete-block walls of the new Facilities Support Center at NASA’s Dryden Flight Research Center during the week of May 21.

The masonry work is expected to be complete by August, followed by construction and installation of the structural steel for the building’s framework, according to Dryden architect Gemma Flores, manager of the project. The structure is currently about 10 percent complete, she added.

The $11.2 million, 38,000-square-foot structure is designed to meet the Leadership in Energy and Environmental Design (LEED) platinum certification standard for environment and energy efficiency.

Designed by the Development One architectural firm of Santa Ana, Calif., the new structure is being built by Comfort and Hays Electric, Inc. of Long Beach, Calif. Contractor officials report the project is a couple of weeks ahead of schedule as they work toward a completion date of July 2013.




All of this week's top headlines to your email every Friday.


 
 

 

News Briefs February 20, 2015

Base Exchange Food Court closure Due to power issues the Base Exchange Food Court operations will be closed through Feb. 22. Unfortunately, the nature of the damage precludes the BX from providing temporary power. As a reminder, other facilities listed below are open for business with the addition of the two food trucks out front:...
 
 
Air Force photograph by Ethan Wagner

Range Commanders Council meets at Edwards

Air Force photograph by Ethan Wagner The 85th Executive Committee of the Range Commanders Council gathered at Edwards Feb. 10 for a two-day conference that ended with a tour of the range. The 85th Executive Committee of the Ran...
 
 
Air Force graphic

Edwards announces new webpage for local STEM needs, support

Air Force graphic In line with Air Force STEM efforts, Team Edwards has created a new webpage for those seeking local STEM programs and support. The new webpage, located at www.edwards.af.mil/stem, which officially went live Fe...
 

 
Air Force photograph by Rebecca Amber

Limited services coming to Edwards AFB’s Veterinary Clinic

Air Force photograph by Rebecca Amber Left to right: Lisa Lage, veterinary technician, assists U.S. Army Capt. Kevin McKenna with Kekoa’s routine nail trim. The boxer’s owner, Jeanette Lovell, stood by to comfort Kekoa ...
 
 

News Briefs February 13, 2015

Base Exchange Food Court closure Due to power issues the Base Exchange Food Court operations will be closed through Feb. 22. Unfortunately, the nature of the damage precludes the BX from providing temporary power. As a reminder, other facilities listed below are open for business with the addition of the two food trucks out front:...
 
 
Air Force image

Visitor Control Center opens March 1

Air Force image The new Visitor Control Center will officially open March 1 outside the West Gate at Century Circle. Members of Team Edwards who use the West Gate daily may have noticed the relatively new building next to Centu...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>