Facilities Support Center construction reaches halfway mark

Arising on what once was known as “Media Hill” in the early days of the Space Shuttle Program, the masonry walls and associated structural steelwork of NASA Dryden’s new Facilities Support Center now grace the center’s campus.

Construction of the new Facilities Support Center at NASA’s Dryden Flight Research Center is proceeding apace, with underground infrastructure and masonry complete and erection of structural steelwork having reached the 90 percent mark by the first week in November.

According to NASA Dryden project architect Gemma Flores, construction of the $11.2 million, 38,000-square-foot structure is about 50 percent finished, with expected completion by July 2013.

Steel decking for the roof has been installed over most of the roof areas within the past two weeks, and grading of the site and pouring of concrete driveways is under way, Flores noted. Work has also begun on installation of interior walls and mechanical ducting.

A steelworker bolts girders in place on the structural steel framework of Dryden’s new Facilities Support Center.

The building will provide office and technical spaces for NASA Dryden’s Facilities Engineering and the Asset Management department as well as the Safety, Health and Environmental Office, combining in one structure functions that are currently performed in several obsolete and inefficient facilities on the Dryden campus. The building plan includes office space, conference rooms, restrooms and shower/changing facilities, workshops, storage mezzanine, laundry and laboratories.

The structure is designed to meet the Leadership in Energy and Environmental Design platinum certification standard for environment and energy efficiency. Based on building energy consumption simulations, NASA Dryden facilities engineers forecast that energy consumption will be reduced about 36 percent over conventional construction.

Designed by the Development One architectural firm of Santa Ana, Calif., the new structure is being built by Comfort and Hays Electric, Inc. of Long Beach, Calif., and its subcontractors.

 




All of this week's top headlines to your email every Friday.


 
 

 

News Briefs July 18, 2014

Express fuel pumps to shut down July 21 & 22 The AAFES Express gasoline station will undergo vapor testing next week, which requires the pumps to be turned off to complete the process.†The fuel pumps will be shut down 8-11 a.m., July 21, and 7 a.m.-1 p.m., July 22. For more information, call (661) 258-1078,...
 
 

Exchange celebrates 119 years with 5 percent MILITARY STAR card discount

July 25, the Army & Air Force Exchange Service marks a historic milestone, celebrating 119 years of serving Soldiers, Airmen and their families. July 25, 1895, General Order No. 46 established the exchange on military installations, directing post commanders to set up an exchange at every post. Since then, the Exchange has supported U.S. troops...
 
 

Focus on deliberate self-development

I am an American Airman. I am a warrior. I have answered my nation’s call. These words should resonate with each of us who have the honor and privilege of wearing the uniform. Each time I recite our creed, I feel a sense of pride. I hope every Airman reading this shares my sentiment. Each...
 

 
Air Force photograph by Rebecca Amber

Edwards says goodbye to Weavers

Air Force photograph by Rebecca Amber Outgoing commander of the 412th Maintenance Group, Col. Robby Weaver (right) receives his retirement pin from his wife Susan during Weaverís retirement ceremony July 10. Weaver and his wif...
 
 
Air Force photograph by Rebecca Amber

Got a ticket? What now?

Air Force photograph by Rebecca Amber 412th Security Forces Squadron defenders pull over a vehicle for speeding. Many drivers have experienced the sinking feeling that accompanies the flashing lights and siren of a police vehic...
 
 

Annual duck blind drawing set for Aug. 9

Waterfowl hunters can participate in the annual duck blind drawing scheduled for Aug. 9 at the Rod and Gun Activity, Bldg. 210. Base hunting permits may be submitted to drawing officials from 9 a.m. until the actual drawing begins, which will be at approximately 10 a.m. Duck blind reservations are required for all base affiliated...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>