Facilities Support Center construction reaches halfway mark

Arising on what once was known as “Media Hill” in the early days of the Space Shuttle Program, the masonry walls and associated structural steelwork of NASA Dryden’s new Facilities Support Center now grace the center’s campus.

Construction of the new Facilities Support Center at NASA’s Dryden Flight Research Center is proceeding apace, with underground infrastructure and masonry complete and erection of structural steelwork having reached the 90 percent mark by the first week in November.

According to NASA Dryden project architect Gemma Flores, construction of the $11.2 million, 38,000-square-foot structure is about 50 percent finished, with expected completion by July 2013.

Steel decking for the roof has been installed over most of the roof areas within the past two weeks, and grading of the site and pouring of concrete driveways is under way, Flores noted. Work has also begun on installation of interior walls and mechanical ducting.

A steelworker bolts girders in place on the structural steel framework of Dryden’s new Facilities Support Center.

The building will provide office and technical spaces for NASA Dryden’s Facilities Engineering and the Asset Management department as well as the Safety, Health and Environmental Office, combining in one structure functions that are currently performed in several obsolete and inefficient facilities on the Dryden campus. The building plan includes office space, conference rooms, restrooms and shower/changing facilities, workshops, storage mezzanine, laundry and laboratories.

The structure is designed to meet the Leadership in Energy and Environmental Design platinum certification standard for environment and energy efficiency. Based on building energy consumption simulations, NASA Dryden facilities engineers forecast that energy consumption will be reduced about 36 percent over conventional construction.

Designed by the Development One architectural firm of Santa Ana, Calif., the new structure is being built by Comfort and Hays Electric, Inc. of Long Beach, Calif., and its subcontractors.

 




All of this week's top headlines to your email every Friday.


 
 

 

News Briefs February 20, 2015

Base Exchange Food Court closure Due to power issues the Base Exchange Food Court operations will be closed through Feb. 22. Unfortunately, the nature of the damage precludes the BX from providing temporary power. As a reminder, other facilities listed below are open for business with the addition of the two food trucks out front:...
 
 
Air Force photograph by Ethan Wagner

Range Commanders Council meets at Edwards

Air Force photograph by Ethan Wagner The 85th Executive Committee of the Range Commanders Council gathered at Edwards Feb. 10 for a two-day conference that ended with a tour of the range. The 85th Executive Committee of the Ran...
 
 
Air Force graphic

Edwards announces new webpage for local STEM needs, support

Air Force graphic In line with Air Force STEM efforts, Team Edwards has created a new webpage for those seeking local STEM programs and support. The new webpage, located at www.edwards.af.mil/stem, which officially went live Fe...
 

 
Air Force photograph by Rebecca Amber

Limited services coming to Edwards AFB’s Veterinary Clinic

Air Force photograph by Rebecca Amber Left to right: Lisa Lage, veterinary technician, assists U.S. Army Capt. Kevin McKenna with Kekoa’s routine nail trim. The boxer’s owner, Jeanette Lovell, stood by to comfort Kekoa ...
 
 

News Briefs February 13, 2015

Base Exchange Food Court closure Due to power issues the Base Exchange Food Court operations will be closed through Feb. 22. Unfortunately, the nature of the damage precludes the BX from providing temporary power. As a reminder, other facilities listed below are open for business with the addition of the two food trucks out front:...
 
 
Air Force image

Visitor Control Center opens March 1

Air Force image The new Visitor Control Center will officially open March 1 outside the West Gate at Century Circle. Members of Team Edwards who use the West Gate daily may have noticed the relatively new building next to Centu...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>