Arising on what once was known as “Media Hill” in the early days of the Space Shuttle Program, the masonry walls and associated structural steelwork of NASA Dryden’s new Facilities Support Center now grace the center’s campus.

Construction of the new Facilities Support Center at NASA’s Dryden Flight Research Center is proceeding apace, with underground infrastructure and masonry complete and erection of structural steelwork having reached the 90 percent mark by the first week in November.

According to NASA Dryden project architect Gemma Flores, construction of the $11.2 million, 38,000-square-foot structure is about 50 percent finished, with expected completion by July 2013.

Steel decking for the roof has been installed over most of the roof areas within the past two weeks, and grading of the site and pouring of concrete driveways is under way, Flores noted. Work has also begun on installation of interior walls and mechanical ducting.

A steelworker bolts girders in place on the structural steel framework of Dryden’s new Facilities Support Center.

The building will provide office and technical spaces for NASA Dryden’s Facilities Engineering and the Asset Management department as well as the Safety, Health and Environmental Office, combining in one structure functions that are currently performed in several obsolete and inefficient facilities on the Dryden campus. The building plan includes office space, conference rooms, restrooms and shower/changing facilities, workshops, storage mezzanine, laundry and laboratories.

The structure is designed to meet the Leadership in Energy and Environmental Design platinum certification standard for environment and energy efficiency. Based on building energy consumption simulations, NASA Dryden facilities engineers forecast that energy consumption will be reduced about 36 percent over conventional construction.

Designed by the Development One architectural firm of Santa Ana, Calif., the new structure is being built by Comfort and Hays Electric, Inc. of Long Beach, Calif., and its subcontractors.

 




All of this week's top headlines to your email every Friday.


 
 

 

News Briefs March 27, 2015

Enlisted promotion ceremony The Edwards Enlisted Promotion Ceremony is 3 p.m., March 31 in the base theater. Promotees and commanders will be in service dress. Uniform of the day for all other attendees will be uniform of the day or business casual. CPTS delayed opening The 412th Comptroller Squadron will delay opening until 11 a.m.,...
 
 

Pursuing dreams to fly, fight and win

Have you ever been told you didn’t have what it takes while pursuing a goal? Did you believe it? I did. My final year in college, the Reserve Officer Training Corps detachment commander met with each senior to discuss our Air Force future. When asked what I hoped to do, like most of my peers...
 
 
Lockheed Martin photograph by Tom Reynolds

Edwards joint maintenance team completes significant JSF propulsion verification event

Lockheed Martin photograph by Tom Reynolds A joint team of U.S. Air Force and U.S. Navy maintainers, DOD employees and Pratt and Whitney contractors work on an F135 engine March 17 as part of a week-long to provide verified tec...
 

 
Air Force photograph by Jet Fabara

Edwards heroes save coworker’s life

Air Force photograph by Jet Fabara Left to right: Moses Zamora, Neil Edwards, Robin “Bubba” Hairston, and Derrick Shannon are heavy equipment operators with the 412th Civil Engineer Group who saved the life of their...
 
 

Edwards CAP squadron to host open house

Edwards AFB’s Civil Air Patrol Squadron will host an open house will be held at the Oasis Community Center 6-8 p.m., March 31. The public is invited to attend and enjoy the squadron cadet program demonstrations. Cadets will be sharing their CAP training experience in the following cadet programs: * Aerospace Education including remotely controlled aircraft and...
 
 
pageant

2015 Edwards Royalty crowned

Courtesy photograph The new Edwards Community Queens were crowned March 21 during the 2015 pageant held at the Oasis Community Center. They are (back row from left) Miss (Danika Blake), Teen Miss (Ariana Medina), Junior Miss (H...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>