Arising on what once was known as “Media Hill” in the early days of the Space Shuttle Program, the masonry walls and associated structural steelwork of NASA Dryden’s new Facilities Support Center now grace the center’s campus.

Construction of the new Facilities Support Center at NASA’s Dryden Flight Research Center is proceeding apace, with underground infrastructure and masonry complete and erection of structural steelwork having reached the 90 percent mark by the first week in November.

According to NASA Dryden project architect Gemma Flores, construction of the $11.2 million, 38,000-square-foot structure is about 50 percent finished, with expected completion by July 2013.

Steel decking for the roof has been installed over most of the roof areas within the past two weeks, and grading of the site and pouring of concrete driveways is under way, Flores noted. Work has also begun on installation of interior walls and mechanical ducting.

A steelworker bolts girders in place on the structural steel framework of Dryden’s new Facilities Support Center.

The building will provide office and technical spaces for NASA Dryden’s Facilities Engineering and the Asset Management department as well as the Safety, Health and Environmental Office, combining in one structure functions that are currently performed in several obsolete and inefficient facilities on the Dryden campus. The building plan includes office space, conference rooms, restrooms and shower/changing facilities, workshops, storage mezzanine, laundry and laboratories.

The structure is designed to meet the Leadership in Energy and Environmental Design platinum certification standard for environment and energy efficiency. Based on building energy consumption simulations, NASA Dryden facilities engineers forecast that energy consumption will be reduced about 36 percent over conventional construction.

Designed by the Development One architectural firm of Santa Ana, Calif., the new structure is being built by Comfort and Hays Electric, Inc. of Long Beach, Calif., and its subcontractors.

 




All of this week's top headlines to your email every Friday.


 
 

 

News Briefs December 19, 2014

Commissary hours The Commissary will be closed Dec. 25 and 26. Regular hours will resume Dec. 27. The Commissary will be open regular hours Dec. 31, and closed Jan. 1, 2015. For more information, call 661-277-9175. Museum hours The Air Force Flight Test Museum will be closed for the Christmas holidays starting Dec. 22 and...
 
 

412th Force Support Squadron Holiday Hours

Christmas Eve: Dec. 24 OPEN: Aero Club: 8 a.m.-4 p.m. Arts & Crafts/Auto Hobby: 9 a.m.-3 p.m. Airman & Family Readiness: 7:30 a.m.-4:30 p.m. Child Development Center: 6:15 a.m.-5 p.m. Family Child Care: 7:30 a.m.-5 p.m. High Desert Inn: Open seven-days a week, 24-hours a day Information, Tickets & Tours: 9 a.m.-5 p.m. Library: 9...
 
 
Air Force photograph by Rebecca Amber

Edwards First Sergeants council wraps up Christmas programs

Air Force photograph by Rebecca Amber The annual Angel Tree program will provide gifts for around 300 Edwards children this year. The Edwards First Sergeants Council puts on the event to help Airmen unable to buy their children...
 

 
afmc-q-and-a

Lean thinking, process improvement highlight Busch’s time at AFMC

During the last 16 years and six assignments in Air Force Materiel Command, Vice Commander Lt. Gen. Andrew Busch was challenged to find new methods to operate more efficiently in one of the most complex and diverse commands tha...
 
 
flu

Flu season: What you need to know

Flu is officially upon us. If you have ever had the flu, you know it can knock you out รณ with members of your family, friends and co-workers not far behind. Today, it’s more important than ever to get your facts straight...
 
 
driving-safety

Driving safely on snow or icy roads

Unless you’re traveling through the mountains of Southern California in the winter, driving in the snow doesn’t occur very often. First off, don’t assume your vehicle can handle any road condition. Even four-w...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>