Commissary parking lot construction plans revised after customer concerns

Tags:
Story and photos by Robert Anderson
Staff writer

Many commissary patrons now find it difficult to park their vehicles in the current parking spaces which are both small and aligned in a parallel fashion. However, once the second half of the parking lot is completed, both halves of the lot will be striped to allow for wider spaces and diagonal parking.

Since construction of the commissary parking lot began on May 7, complaints and concerns about the project have flooded the inboxes of commissary and garrison leadership, and these have not gone unchecked.

The complaints that have been logged against the parking lot construction project range from design flaws to pedestrian safety issues, while traffic flow and small parking spaces seem to be the major concerns.

John Ruble, Directorate of Public Works director, assures commissary patrons that all the issues have been addressed and new plans have been drawn up to correcting the problems.

“With the original plan we had 263 total spaces; initially the intent was to maximize parking. When we stripe it diagonally, it will go down to 236 total spaces. Handicap assessable, van accessible, motorcycle and employee parking will all stay the same. It is the standard spaces that make up the difference,” Ruble explained.

Although this reduces the number of spaces by 27, this is an increase of 22 spaces from the original parking lot’s 204 spaces.

“We are widening the stalls from 8 feet 9 inches to 9-and-a-half feet. This will make a difference … it is a little tight [current parking spaces] with big trucks and SUVs. I think it will work a lot better,” Ruble said.

Work is underway on the second half of the commissary parking lot. Once the project is entirely finished, officials hope it will meet customer needs and add to the overall quality of the commissary shopping experience.

The project is being implemented in two phases. The first phase is the completed section of the parking lot that has received the above-mentioned complaints from commissary patrons. The second phase is the half of the parking lot currently under construction and will include the changes that were prompted by the said complaints.

Ruble details the new timeline.

“The second phase should be completed September 1. Then we will close the section that is open, seal-coat it and stripe it, and the entire lot should be open September 8.”

Col. Dan McFarland, commander, United States Army Garrison, Fort Huachuca, also wanted to reassure commissary patrons their concerns have been addressed and clarify any misunderstandings about the project.

About the parking lot design McFarland said, “The current one [design] meets the standards, and is comparable to Wal-Mart or Target. But, we realize sometimes we have to go beyond those standards,” McFarland said.

“We heard the consumers’ concerns; they were valid, and we responded to them. We cannot respond to every complaint, but in this particular case, we will go back and redo it,” McFarland added.

The redesigned, finished parking lot will offer commissary patrons one-way parking lanes with larger spaces. New eight-foot pedestrian walkways have been added for customer safety. And the low impact design of the new parking lot will capture six to eight acre-feet of storm water recharge.

“The direct beneficiaries of the new parking lot are the people that use the commissary; and as small as a parking lot may seem, it’s not such a small matter for someone trying to push a shopping cart full of food,” McFarland said.

“The new parking lot will add to our water conservation efforts, and with the landscaping, will be a really good presentation,” he added.




All of this week's top headlines to your email every Friday.


 
 

 

FH schools to celebrate National Bike to School Day March 06

Students from Colonel Johnston, General Myer and Colonel Smith Middle Schools will be riding or walking to school on March 6 along with parents, teachers and community leaders. The event will begin from 7 to 8:30 a.m. with youth, parents and community leaders riding or walking from parking lot locations listed below or from home....
 
 

Chalk Talk

Colonel Johnston Elementary School History will come to life in Amy Sullins’ second grade classroom on Tuesday. Students have been researching a famous person from the American Revolution or Westward Expansion. They are writing a short biography and memorizing a speech in the first person. They will come to school dressed as their person and...
 
 
Courtesy photo

Diving platform at Barnes Field House helps with Soldier training

Courtesy photo A Soldier in full uniform jumps down from a platform mounted 6 feet above the pool at Barnes Filed House. The platform was installed to give a semblance of realism to water safety training offered here and make a...
 

 
photo

Chalk Talk

Colonel Johnston Elementary School History will come to life in Amy Sullins’ second grade classroom on March 3. Students are researching a famous person from the American Revolution or Westward Expansion. They are writing a s...
 
 

Prescribed burning to take place on Fort Huachuca

Sierra Vista — Coronado National Forest, Sierra Vista Ranger District, in collaboration with Fort Huachuca will begin spring-season prescribed fires on Fort Huachuca Monday – Wednesday. Prescribed fire activities are expected to continue throughout the year when favorable weather permits. Current plans include three prescribed fire areas totaling approximately 4,700 acres. The areas to be...
 
 

Outreach Ministries Program coordinator retires after 47 years

The longtime Chapel Outreach Ministries Program director is retiring from the federal government after 47 years of civil service. Jo Moore, a Fort Huachuca Main Post Chapel icon, has spent the past 31 years of her civil service working for the chapel on the installation. During her tenure, she and the programs she started have...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>


Directory powered by Business Directory Plugin