KC-46 critical design review nearing completion

The KC-46A is intended to replace the U.S. Air Force’s aging fleet of KC-135 Stratotankers which has been the primary refueling aircraft for more than 50 years. With more refueling capacity and enhanced capabilities, improved efficiency and increased capabilities for cargo and aeromedical evacuation, the KC-46A will provide aerial refueling support to the Air Force, Navy, Marine Corps as well as allied nation coalition force aircraft.

WASHINGTON (AFNS) – The Air Force and Boeing successfully conducted the KC-46 critical design review, or CDR, from July 8-10 at the Boeing facility in Mukilteo, Wash.

The KC-46 weapon system CDR was the culmination of nine months of component and sub-system design reviews, which blended the best practices of both the commercial and Department of Defense frameworks.
Currently, the CDR still has a few actions to finish, but the process is scheduled to be complete well in advance of the Sept. 24 contractual date.

“The efforts by the combined Boeing and Air Force team to get to this point in the program development have been tremendous,” said Maj. Gen. John Thompson, the program executive officer for tankers. “For the warfighter, completion of this milestone is a big step forward toward beginning the recapitalization of the Air Force’s legacy KC-135 fleet, delivering advanced and improved multi-mission capabilities to the fight on day one.”

Attendees at the meetings included the Government KC-46 Program Office, Boeing, Air Mobility Command, Air Force and Department of Defense test and acquisition leaders, and the Federal Aviation Administration.

Thompson said that the overall design maturity of the tanker is at a high level, grounded in the commercial-derivative nature of the design approach, which is based on the Boeing 767.

Once the CDR is complete, Boeing will proceed into the fabrication, hardware and software integration, and test phase of the KC-46 development program.

The Air Force contracted with Boeing in February 2011 to acquire 179 KC-46 Tankers to begin recapitalizing the more than 50-year-old KC-135 fleet. The initial delivery target is for 18 tankers by 2017. Production will then ramp up to deliver all 179 tankers by 2028.

The first fully-equipped KC-46 is projected to fly in early 2015 in support of engineering and manufacturing development activities.




All of this week's top headlines to your email every Friday.


 
 

 

BASH: Protecting our aircraft, Airmen

U.S. Air Force photo/2nd Lt. Bari Wald David Briseño, wildlife biologist with the United States Department of Agriculture and head of Marchs’ Bird/Anti-Aircraft Strike Hazard (BASH) program, prepares to fire a 12-gauge ‘shell cracker’ into the air with his shotgun. Firing ‘shell crackers’ is one of many pyrotechnic methods used in the BASH program to...
 
 
US_Air_Force_Logo

Strategic agility is the future of the Air Force

WASHINGTON (AFNS) — As the Air Force prepares for new challenges and opportunities of the coming decades, it faces sobering 21st-century realities: global centers of power have become more distributed and the terrorism th...
 
 

SECAF: Air Force grapples with Congress to fund readiness

WASHINGTON (AFNS) — To balance readiness today and modernization tomorrow, the Air Force’s fiscal year 2015 budget request is shrinking like today’s defense budget thanks to Congress’s own priorities and the approaching threat of sequestration in 2016, Air Force leaders said July 30. Secretary of the Air Force Deborah Lee James and Air Force Chief...
 

 
BlueTube

Voting now open for American Airman Video Contest

  Voting for the 2014 American Airman Video Contest is now open and runs until Aug. 22 at 3 p.m. CDT. The contest launched July 1 for all Total Force Airmen to showcase their Air Force stories in short selfie videos. “Ev...
 
 

AF implements career intermission pilot program

WASHINGTON — Up to 40 active-duty, Air Force Reserve and Air National Guard officers and enlisted members who meet eligibility requirements will be offered between one and three years of partially-paid time out of uniform to focus on personal and professional pursuits under the Career Intermission Pilot Program, or CIPP, Air Force officials announced July...
 
 

Air Force to change enlisted evaluations, promotions

WASHINGTON (AFNS) — Air Force officials announced a series of sweeping changes to the Enlisted Evaluation System and Weighted Airman Promotion System (WAPS) July 31. The changes are intended to ensure the Air Force truly makes job performance the driving factor and will be implemented incrementally beginning in August 2014 and continuing through early 2016....
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>


Directory powered by Business Directory Plugin