Local

August 10, 2012

Construction continues on water lines

By 99th Air Base Wing Public Affairs
U.S. Air Force photo by Airman 1st Class Christopher Tam
Transwest construction personnel install a pipeline for a water pipe construction project Aug. 8, 2012, at Nellis Air Force Base, Nev. The project will improve potable water quality for the many users served by the existing 60-year-old Tyndall Ave. water main and will increase the water quantity available to the base fire department for airfield and base fire-fighting requirements.

NELLIS AIR FORCE BASE, Nev. — Construction began on an existing 60-year-old water line along Tyndall Avenue and the flightline here in September 2010 and continues today due to more than 100 differing site conditions encountered by the contractor.

These unexpected problems have delayed project completion and increased the cost.

“This project has been a voyage of discovery, with the contractor repeatedly unearthing a labyrinth of aged and corroded utilities and hidden structural problems that added time and cost to the effort,” said Col. Barry Cornish, 99th Air Base Wing commander.

The project was contracted out because the water lines were badly deteriorated.

“Corrosion had restricted the effective pipe area so that flows and pressures were below acceptable code requirements, especially for fire protection,” said Frank Wertin, 99th Civil Engineer Squadron, chief of project management. “Most of the existing valves were no longer functional and couldn’t be closed to enable isolation of sections of lines for repair.”

The contract required the replacement of more than 20,000 linear feet of polyvinyl chloride distribution water mains, including new fire hydrants and other items. Work on the water mains had to be phased in and coordinated to allow for continued aircraft and vehicle operations, use of and access to the flightline service road and aircraft hangars and their approach aprons and to Tyndall Ave., as well as the facilities used by base personnel.

Work also included removal and replacement of trenched sections of Portland cement airfield pavement, hot mix asphalt roads and parking lots, concrete masonry unit walls, a chain link fence, and other obstacles.

“This has been perhaps the most challenging project and one with the largest physical impact of any project attempted at Nellis in the past 30 years,” Wertin said.

The work is about 80 percent complete. The contractor still needs to tie facilities to the new water system, finish installation of the main on the flightline and install permanent pavement repairs on both Tyndall Ave. and the flightline pavements. This should start within the next few weeks.

Over the next four months, most of the facilities along Tyndall Ave from the Tyndall Gate to Beale Ave will incur temporary water outages as the buildings, starting from the south end, will be tied into the new water line. Outages will be a short as possible but could be as long as 10 hours and several facilities will be affected during each outage. Specific outage times will be coordinated in advance with facility managers and they will be notified when the outage is approved so they can inform the building occupants. Port-a-potties will be placed adjacent to facilities for use during the outages.

The new contract completion date is Dec. 31.




All of this week's top headlines to your email every Friday.


 
 

 

First enlisted Airmen awarded Weapons School graduate patches

NELLIS AIR FORCE BASE, Nev. — History was made June 27, when five graduates of the U.S. Air Force Weapons School’s Joint Terminal Attack Controller Weapons Instructor Course became the first enlisted Airmen in the school’s 66-year mission to be awarded the Weapons School’s graduate patch. These graduates will now be recognized as subject matter...
 
 

Staying safe during flash flood season

NELLIS AIR FORCE BASE, Nev. — July is here with high temperatures and a high chance of flash flooding. The months with the highest probability for thunderstorms are July through September. Las Vegas’ annual rainfall is approximately 4.13 inches, and while this may not seem like a lot of rain, the elevation of Las Vegas...
 
 

Conquer fear, live your dream

VANCE AIR FORCE BASE, Okla. — Are you living the dream? Do you wake up with energy each morning or do you need an energy drink to get you going? If you constantly hit the snooze button on your alarm, wake with no energy and low self-esteem, need lots of coffee, soda or energy drinks...
 

 
U.S. Air Force photo by Senior Airman Joshua Kleinholz

Weapons School honors newest graduates

U.S. Air Force photo by Senior Airman Joshua Kleinholz Gen. Lori Robinson, Pacific Air Forces commander, delivers the keynote speech during the U.S. Air Force Weapons School Class 15-A graduation ceremony in Las Vegas, Nev., Ju...
 
 
U.S. Air Force photo illustration by Tech. Sgt. Nadine Y. Barclay

Hunters save lives through RPA Human Performance Team

U.S. Air Force photo illustration by Tech. Sgt. Nadine Y. Barclay Considering the demands facing the remotely piloted aircraft enterprise, Team Creech has formed their own human performance team to meet the needs of those suppo...
 
 
Courtesy photo

Employment Assistance Program aids military members’ transition

Courtesy photo Members of the Nellis community attend a job fair as part of the Airman and Family Readiness Center’s Employment Assistance Program at Nellis Air Force Base, Nev., April 23. The Employment Assistance Program he...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>