Local

August 10, 2012

Construction continues on water lines

By 99th Air Base Wing Public Affairs
U.S. Air Force photo by Airman 1st Class Christopher Tam
Transwest construction personnel install a pipeline for a water pipe construction project Aug. 8, 2012, at Nellis Air Force Base, Nev. The project will improve potable water quality for the many users served by the existing 60-year-old Tyndall Ave. water main and will increase the water quantity available to the base fire department for airfield and base fire-fighting requirements.

NELLIS AIR FORCE BASE, Nev. — Construction began on an existing 60-year-old water line along Tyndall Avenue and the flightline here in September 2010 and continues today due to more than 100 differing site conditions encountered by the contractor.

These unexpected problems have delayed project completion and increased the cost.

“This project has been a voyage of discovery, with the contractor repeatedly unearthing a labyrinth of aged and corroded utilities and hidden structural problems that added time and cost to the effort,” said Col. Barry Cornish, 99th Air Base Wing commander.

The project was contracted out because the water lines were badly deteriorated.

“Corrosion had restricted the effective pipe area so that flows and pressures were below acceptable code requirements, especially for fire protection,” said Frank Wertin, 99th Civil Engineer Squadron, chief of project management. “Most of the existing valves were no longer functional and couldn’t be closed to enable isolation of sections of lines for repair.”

The contract required the replacement of more than 20,000 linear feet of polyvinyl chloride distribution water mains, including new fire hydrants and other items. Work on the water mains had to be phased in and coordinated to allow for continued aircraft and vehicle operations, use of and access to the flightline service road and aircraft hangars and their approach aprons and to Tyndall Ave., as well as the facilities used by base personnel.

Work also included removal and replacement of trenched sections of Portland cement airfield pavement, hot mix asphalt roads and parking lots, concrete masonry unit walls, a chain link fence, and other obstacles.

“This has been perhaps the most challenging project and one with the largest physical impact of any project attempted at Nellis in the past 30 years,” Wertin said.

The work is about 80 percent complete. The contractor still needs to tie facilities to the new water system, finish installation of the main on the flightline and install permanent pavement repairs on both Tyndall Ave. and the flightline pavements. This should start within the next few weeks.

Over the next four months, most of the facilities along Tyndall Ave from the Tyndall Gate to Beale Ave will incur temporary water outages as the buildings, starting from the south end, will be tied into the new water line. Outages will be a short as possible but could be as long as 10 hours and several facilities will be affected during each outage. Specific outage times will be coordinated in advance with facility managers and they will be notified when the outage is approved so they can inform the building occupants. Port-a-potties will be placed adjacent to facilities for use during the outages.

The new contract completion date is Dec. 31.




All of this week's top headlines to your email every Friday.


 
 

 
DT3

Armory ensures defenders locked, loaded

U.S. Air Force photo by Airman 1st Class Thomas Spangler Senior Airman Ian Bonilla, 99th Security Forces Squadron armorer, test fires an X-26 Taser at the armory, Nellis Air Force Base, Nev., Sept 16. Bonilla test fired each ta...
 
 
DT-140826-F-IF502-009

Radiology: Finding mysteries within

U.S. Air Force photo by Airman 1st Class Thomas Spangler Airman 1st Class Cassandra Caballero, 99th Medical Surgical Operations Squadron diagnostic imaging phase two student, demonstrates correct form for receiving a chest X-ra...
 
 
DT-2

Always vigilant: Command post provides oversight, assistance

Tech. Sgt. Laura Langley (left) and Senior Airman Sarah Myers, 99th Air Base Wing Command Post senior and junior controllers, field phone calls at their workstations at Nellis Air Force Base, Aug. 21. Command post controllers a...
 

 
U.S. Air Force photo illustration by Airman 1st Class Rachel Loftis

CDOS 2014 comes to a close

U.S. Air Force photo illustration by Airman 1st Class Rachel Loftis Many people view the Labor Day weekend as the end of summer and a last chance to travel, hit Lake Mead, fire up the grill or indulge in their favorite outdoor ...
 
 

Lomie G. Heard Elementary School faculty looking forward to new school year

U.S. Air Force photo by Airman 1st Class Mikaley Towle Dominga Romero (left), special programs teacher assistant, and Terri Gravnitz (right), early childhood special education teacher, prepare their classroom for the start of the new school year at Lomie G. Heard Elementary School on Nellis Air Force Base, Nev., Aug. 21. The new school year...
 
 
U.S. Air Force photo by Tech. Sgt. Nadine Barclay

Get your caffeine at Coolbeans café

U.S. Air Force photo by Tech. Sgt. Nadine Barclay The Coolbeans Café, a coffee shop serving Starbucks is now open in Hangar 1003 to serve the Airmen of Creech Air Force Base. Airmen interested in getting out of their work cent...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>


Directory powered by Business Directory Plugin