The solar field, comprised of more than 72,000 panels, was completed after 26 weeks of construction and three years of planning. The array is expected to produce more than 25 percent of Nellis’ electricity.

TYNDALL AIR FORCE BASE, Fla. — The Air Force is set to outdo itself with another large solar project at Nellis Air Force Base. SunPower Corporation completed a 14-megawatt solar power system at Nellis in 2007.

At the time, it was the largest solar photovoltaic power plant in the United States. Recently the Air Force signed a lease with NV Energy paving the way for construction of a 19-megawatt solar photovoltaic power system at Nellis to be built by SunPower.

“We are pleased to team again with NV Energy,” said Howard Wenger, SunPower’s regions president. “In 2007, it took nine months to construct the 14-megawatt plant at Nellis. Today, we can install more than one megawatt per day at our larger power plant sites.”

Construction is contingent on Nevada’s Public Utilities Commission approving the contract. Renewable energy from both solar arrays could provide 42 percent of the energy needed to power the base.

“NV Energy looks forward to the opportunity to bring cleaner, renewable energy to power facilities and military operations at Nellis,” said Stacey Kusters, NV Energy’s vice president for renewable energy.

NV Energy will construct, own, maintain and operate the array. All power from the photovoltaic array will flow through the installation. Power not used by the base will go to the grid. Nellis will purchase power at the existing NV Energy tariff rate under the existing utility contract. NV Energy will provide a secondary substation as an in-kind consideration to the government for the lease.

“This is a huge benefit to the Air Force,” said Frederick Cade, project manager at the Air Force Civil Engineer Center. “It affords Nellis much needed energy security and mission assurance by providing a redundant primary electric feed to the installation.”

“It’s exciting to see Nellis Solar II coming to fruition,” said Lynn Haarklau, 99th Civil Engineer Squadron asset optimization chief. “A lot of Air Force and NV Energy folks have worked hard and put in long hours to ensure the success of this project. It’s extremely gratifying to know that all our efforts are paying off by providing Nellis with a mission-critical redundant power source.”

The project is a combined effort by Nellis, Air Combat Command and AFCEC. The installation conducted the National Environmental Policy Act process, gained acceptance of the project with other installation agencies and coordinated with NV Energy. ACC evaluated the economic viability and provided expertise for the Power Purchase Agreement. AFCEC provided overall project oversight and served as the liaison with senior Air Force leadership by providing updates on project plans, execution and scheduling. In addition, AFCEC and Air Force general counsel led the real estate actions and development of the lease.

Based on data derived from the U.S. Environmental Protection Agency’s greenhouse gas equivalencies calculator, the new plant will offset the annual production of almost 27,000 tons of carbon dioxide emission, which is equivalent of removing 136,800 cars from Nevada’s roads over the next 31 years.




All of this week's top headlines to your email every Friday.


 
 

 
U.S. Air Force photograph by Senior Airman Thomas Spangler

LVC integration takes Red Flag to next level

U.S. Air Force photograph by Senior Airman Thomas Spangler Airmen participate in the live, virtual, constructive portion of Red Flag 15-2 at the Combined Operations Center-Nellis on Nellis Air Force Base, Nev., March 5. Red Fla...
 
 

AF wounded warrior trials in full swing at Nellis

NELLIS AIR FORCE BASE, Nev. — The 2015 Air Force Trials are underway after an opening ceremony to welcome the warriors here, Feb. 27. This year marks the second occurrence of the Air Force Trials, both taking place at Nellis Air Force Base. The trials are intended to promote the health and wellness of seriously...
 
 

99th FSS leads charge during wounded warrior trials

NELLIS AIR FORCE BASE, Nev. — The 99th Force Support Squadron transformed the Warrior Fitness Center’s facilities for the second consecutive year into a bustling adaptive sports competition for roughly 100 wounded warriors known as the 2015 Air Force Trials, which took place here Feb. 27 through March 5. “The amount of support we get...
 

 
Tbirds

Thunderbirds prepare for ACC commander

The U.S. Air Force Air Demonstration Team, the Thunderbirds, perform a demonstration in preparation for the commander of Air Combat Command at Nellis Air Force Base, Nev., March 2. The Thunderbirds Showline consists of 24 profe...
 
 
U.S. Air Force photo by Senior Airman Thomas Spangler

Base construction set to cut costs, update facilities

U.S. Air Force photo by Senior Airman Thomas Spangler A construction worker operates a wheel loader during the demolition of the old gym near the exchange at Nellis Air Force Base, Nev., Oct. 29, 2014. The demolition of the old...
 
 

99th LRS implements AIM2

NELLIS AIR FORCE BASE, Nev. — Nellis AFB recently underwent a major change on how ground fuels are issued at the Military Service Station here. A Defense Logistics Agency contractor, Syn-Tech, installed a new Automotive Information Module, or AIM2 Vehicle Radio Frequency Technology, on approximately 500 Air Force vehicles located at Nellis AFB. The AIM2...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>


Directory powered by Business Directory Plugin