Defense

April 3, 2012

C-27 program cut explained, budget aligned with strategy

by TSgt. Jess Harvey
Air Force News

The Air Force deputy chief of staff for strategic plans and programs discussed the reasoning behind the C-27J Spartan program cut from the fiscal 2013 budget request during the Air Force Association’s monthly breakfast seminar March 27.

“It’s not because it isn’t a good aircraft, and it’s not because it wasn’t a good idea $487 billion ago,” said Lt. Gen. Christopher Miller. “We are going to make more disciplined use of defense dollars.”

From a financial and programmatic perspective, anytime an entire weapons system, its logistic support and training infrastructure can be eliminated without harming the capabilities of the force, the benefits are greater, Miller said.

“The savings that you reap from that kind of action is far greater than if you just retired a fractional number of the fleet,” he said.

Coupling the facts that the Air Force was under financial pressure and the life-cycle costs of the C-27 exceeded that of the C-130 Hercules because of how it was to be based, there wasn’t any other realistic option, especially given that the Air Force can accomplish its goals with the C-130, according to Miller. “We remain committed to supporting our Army teammates.”

“(Cutting the C-27 program) was a decision we did not like to make, but that we had to make,” he said. “Its capacity, over and above the rest of the fleet, simply was not needed under the demands of the new strategy. What that allowed us to do was keep some very important things on track.”

He said the savings allowed the Air Force to maintain focus on systems like the KC-46A Tanker and the F-35 Lightning II joint strike fighter as well as other, not-so-visible systems like global positioning satellites, space programs, and intelligence, surveillance and reconnaissance systems.

“We want to make decisions in the near term that support the strategic vision in the long term,” Miller said. “As we start to come out of Afghanistan, and have come out of Iraq, we are facing a new resource era.”

He said the Air Force is looking at a type of full-spectrum rebalancing within the force.

“We’re trying to bring all these things we’ve done for a long time into a sustainable balance for the future,” the general said. “Space and cyber are clearly more predominant in all aspects of military operations than they used to be.”

The Air Force is going to put even more emphasis on making sure the active, Guard and Reserve components are balanced appropriately and making sure Airmen and assets are fully ready all the time, he said.

“Maintaining a smaller force that is anything less than ready is a bad idea,” said Miller.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines March 27, 2015

News General Dynamics withdraws as T-100 prime contractor General Dynamics Information Systems and Technology has withdrawn itself as the prime contractor on the T-100, the offering for the T-X trainer replacement program based on the Alenia Aermacchi M-346 design.   Business SpaceX’s fight with U.S. Air Force called a clash of perceptions Billionaire Elon Musk’s...
 
 

News Briefs March 27, 2015

Contractor extradited from Iraq pleads guilty in bribes case A man extradited from Iraq in a military contract bribery case has pleaded guilty to three charges in an agreement with federal prosecutors. U.S. District Judge Thomas Rose has scheduled sentencing for July 1 for Metin Atilan. His attorney, Nick Gounaris, says the two sides agreed...
 
 

Ninth Boeing GPS IIF reaches orbit, sends first signals

Boeing Global Positioning System (GPS) IIF satellites are steadily replenishing the orbiting constellation, continuing to improve reliability and accuracy for users around the world. The ninth GPS IIF reached orbit about three hours, 20 minutes after launching today aboard a United Launch Alliance (ULA) Delta IV rocket from Cape Canaveral Air Force Station, Fla., and...
 

 

F-35 Lightning II costs drop, report shows

A recent account of F-35 Lightning II aircraft program costs shows decreases, the Air Force’s F-35 program executive officer told reporters in a media roundtable March 24, 2015. Lt. Gen. Christopher C. Bogdan, citing this year’s selected acquisition report on the aircraft, called the roundtable to clarify cost and performance facts. He also acknowledged the...
 
 
NG-growler2

Northrop Grumman delivers center/aft ‘shipset’ for first international EA-18G Growler

Northrop Grumman photograph Northrop Grumman mechanics perform final quality inspections on the center/aft fuselage shipset produced by the company for the first Australian EA-18G Growler. The subassembly will be delivered to B...
 
 
Navy photograph by Monica McCoy

Navy conducts production acceptance test of Tomahawk missile

Navy photograph by Monica McCoy Members of the Explosive Ordnance Disposal Technology Division team at Naval Surface Warfare Center, Indian Head prepare a Tomahawk missile for a functional ground test at the Large Motor Test Fa...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>