Radar program proceeding with revised acquisition strategy

by Patty Welsh
Hanscom AFB, Mass.

The Air Force program to provide a new ground-based, long-range radar system is moving forward with a revised acquisition strategy. The program office recently held an industry day here to explain the changes and its latest draft request for proposal.

The Three-Dimensional Expeditionary Long-Range Radar, or 3DELRR, will be the principal U.S. Air Force long-range, ground-based sensor for detecting, identifying, tracking, and reporting aircraft and missiles in support of theater commanders. It will replace the current Air Force radar, the TPS-75.

“A combination of several factors, including a somewhat atypical acquisition strategy and the U.S. budget crisis, led to the change,” said Lt. Col. Brian McDonald, 3DELRR program manager.

A September 2007 memorandum from John Young, then the acting undersecretary of Defense for Acquisition, Technology, and Logistics, encouraged competitive prototyping up to Milestone B. Originally, the 3DELRR Program had been planning to award to a single contractor prior to Milestone B.

“We modified the strategy to further leverage competition to look at needed capability, different approaches to delivering that capability and doing so in the most affordable manner,” McDonald said.

During the industry day briefing, he also showed how the program budget had been reduced in the Fiscal Year 2013 President’s Budget by approximately $80 million over the next five years compared to the 2012 budget.

McDonald cited industry offerings as a third factor.

During his presentation in the base theater, McDonald walked through a graphical depiction of the revised acquisition strategy and the changes that have been made.

Now, up to three contracts may be awarded as an outcome of the upcoming full and open competition to complete the Technology Development Phase, referred to as the Pre-Engineering and Manufacturing Development (Pre-EMD) period. The 3DELRR source selection will use the lowest price technically acceptable approach, which is also a significant change.

“Competitive offerors must be at the same maturity level as the government has attained on this program,” said McDonald. “We do not want to turn back the clock. We want to move forward from the government investment to date.”

In addition, fixed price contracts, including Firm Fixed-Price and/or Fixed-Price Incentive Firm, are planned for the Pre-EMD, EMD, and low rate initial production phases from what was once a cost plus incentive fee approach.

The revised strategy includes a minimum of three full and open competitions to reach full operational capability. McDonald pointed to the third competition that will award scope beyond Milestone B to a single contractor.

“There will be much activity, in parallel, leading up to Milestone B,” explained McDonald. “We will need a strong, crisp effort by industry on these contracts while the program office simultaneously conducts the next source selection and prepares for Milestone B.”

One change that McDonald strongly emphasized was the early examination of cost versus capability trade-offs. While there has been no change in the 3DELRR requirements since Technical Requirement Documents Revision D was posted in October 2011, McDonald explained the plan to issue a new revision, during the period of performance, against which successful bidders would produce their preliminary designs.

“We need to look closely at cost versus capability,” he said. “The first contractual activity is to complete detailed analyses of top cost drivers to see how cost varies as capability is incremented. Are there relatively large cost savings to be gained by relatively small reductions in capability and, if so, what’s the risk?”

McDonald discussed how the acquisition community and operational community will then come together to set 3DELRR requirements.

The 3DELRR program has also been selected as a “designated system” to participate in the Defense Exportability Features Pilot Program, to potentially increase sales and lower production costs.

“I’m excited to be a pilot for the Defense Exportability Features Program because it’s forward thinking, it’s good for the U.S. government and it’s good for U.S. industry,” McDonald said. Addressing the audience of mostly company representatives, he added, “I hope you’re excited too.”

The 3DELRR Program Office is planning for a Defense Acquisition Board in late April and, if approved, anticipates release of the final RFP in May. Currently, the program office expects to award the contracts, totaling approximately $108 million dollars, by late August.

“No one is immune from the budget crisis,” said McDonald. “This acquisition strategy is our response. Now, we need strong industry performance to offer the most affordable solution that provides this needed capability to our warfighters.”

More information on the 3DELRR program, as well as solicitation details, can be found on the FedBizOpps website at https://www.fbo.gov.




All of this week's top headlines to your email every Friday.


 
 

 
University of Rhode Island photograph by Tom Glennon

NASA kicks off field campaign to probe ocean ecology, carbon cycle

University of Rhode Island photograph by Tom Glennon The Research Vessel Endeavor is the floating laboratory that scientists will use for the ocean-going portion of the SABOR field campaign this summer. NASA embarks this week o...
 
 
NASA photograph by Carla Thomas

NASA’s high-flying laser altimeter to check out summer sea ice, more

NASA photograph by Carla Thomas This summer, the Multiple Altimeter Beam Experimental Lidar, or MABEL, will fly above Alaska and the Arctic Ocean on one of NASA’s ER-2 high-altitude aircraft. Sea ice in summer looks dramatica...
 
 
SOFIA

Outer space to inner space: SOFIA inside Lufthansa Technik hangar

NASA photograph by Jeff Doughty NASA’s Stratospheric Observatory for Infrared Astronomy is shown inside the Lufthansa Technik hangar in Hamburg, Germany where it is beginning its decadal inspection. Flight, aircraft maint...
 

 
NASA photograph by Tony Landis

New life for an old bird: NASA’s F-15B test bed gets new engines

NASA photograph NASA’s F-15B flight research test bed carries shuttle thermal insulation panels on its underbelly during a research flight in 2005. NASA Armstrong’s F-15B aeronautics research test bed, a workhorse at th...
 
 
NASA photograph by Tom Tschida

Towed glider benefits from center’s new 3-D printer capability

NASA photograph by Tom Tschida The major components of NASA Armstrong’s new high-resolution 3-D additive manufacturing printer occupy a shelf in the center’s subscale aircraft research lab. Robert “Red” ...
 
 
NASA photograph by Emmett Given

NASA completes testing on 3-D printer

NASA photograph by Emmett Given United Space Alliance engineer Cynthia Azzarita, left, and Boeing Company engineer Chen Deng, members of the Human Factors Integration Team at NASA’s Johnson Space Center, conduct a “...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>