Defense

May 4, 2012

GAO look sat F-22 modernization program

by Marti Jaramillo
staff writer

The Government Accountability Office was recently asked to examine the history of modernization programs of many of its fighter and attack aircraft and make comparisons with the F-22A modernization program, which will develop and retrofit new capabilities onto a complex stealth aircraft through 2023.

Programs examined and compared included the F-15, F-16 and F/A-18.

GAO officials stated in their report, that they had reviewed official service history documents and current and historical program documents; analyzed program cost, schedule, performance, and quantity data; and spoke with current and former Air Force, Navy, and contractor officials.

The F-22A began as a single-step program and did not anticipate the need for future modernization, while the other legacy programs each began with the expectation that their aircraft would be incrementally upgraded over time.

Nearly all of the F-22A modernization upgrades would have to be retrofitted onto fielded aircraft while, legacy modernization programs integrated their upgrades into new production aircraft, had fewer complexities, and were thus less costly.

Originally designed to counter air threats posed by the former Soviet Union, the post-Cold War era spurred efforts to add new missions and capabilities to the F-22A, including improved air-to-air and robust air-to-ground attack and capabilities.

“The F-22A modernization began in reaction to a major shift in the aircraft’s basic mission, which required the development of new capabilities that had not been planned for as part of the initial development program,” said GAO officials. “In contrast, the legacy modernization programs all made planned incremental improvements to existing mission capabilities.”

Although the legacy and F-22A programs began modernizing at the same general points in time, the F-22A modernization program resources, primary technology and funding needed to meet the new requirements had not been fully developed or identified.

This means that many of the Air Force’s F-22 Raptors may not get their long-promised capability upgrades until well into their service lives. Calculations show that this would mean that the improvements would not be completed until the aircraft reaches nearly 20 percent of their 8,000-hour service life.

Each of the programs, including the F-22A, initially managed and funded modernization as a continuation of its baseline program, so modernization costs and funding were not clearly identified in selected acquisition reports or budget documents.

As a result, the cost, schedule and performance projections for the F-22A modernization program were not well founded.

According to a separate GAO report to the Subcommittee on Defense, Committee on Appropriations and the U.S. Senate, the program now faces cost, technical and sustainment risks.

The GAO found that the total projected cost of the F-22A modernization program and related reliability and maintainability improvements more than doubled since the program started – from $5.4 billion to $11.7 billion-and the schedule for delivering full capabilities slipped seven years, from 2010 to 2017.

The Air Force and Navy have modernized many of their fighter and attack aircraft over the past several decades and given this historical experience, there are definitely concerns about the mounting cost of F-22A modernization.

The Air Force currently plans to spend about $11.7 billion to modernize and improve the reliability of the F-22A. About $9.7 billion will be spent on specific modernization increments and related support costs, and nearly $2 billion will be used to improve the reliability of the F-22A and make structural repairs.

The GAO report also said the content, scope and phasing of planned capabilities has also shifted over time with changes in requirements, priorities and annual funding decisions. Visibility and oversight of the program’s cost and schedule is hampered by a management structure that does not track and account for the full cost of specific capability increments. Substantial infrastructure costs for labs, testing, management, and other activities directly support modernization but are not charged to its projects.

The GAO found that the testing of new capabilities to ensure operational effectiveness and suitability would be ongoing. Results to date have been satisfactory but development and operational testing of the largest and most challenging sets of capabilities have not yet begun.

Going forward, major challenges will be developing, integrating and testing new hardware and software to counter emerging future threats. Other risks are associated with greater reliance on laboratory ground tests and relocating an F-22A lab needed to conduct software testing.

While modernization is under way, the Air Force has undertaken parallel efforts to improve F-22A reliability and maintainability to ensure life-cycle sustainment of the fleet is affordable and to justify future modernization investments. But the fleet has not been able to meet a key reliability requirement, now changed, and operating and support costs are much greater than earlier estimated.

In 2003, the Air Force established the F-22A modernization program to develop and insert new capabilities in four increments.

The GAO recommended that the Defense Department evaluate capabilities to determine if future F-22A modernization efforts meeting DOD policy and statutory requirements should be established as separate major acquisition programs.

According to David G. Ahern, Deputy Assistant Secretary of Defense Strategic and Tactical Systems, DOD concurred with the recommendation.

The Air Force will therefore move forward with plans to manage its fourth modernization increment as a separate major acquisition program.

The GAO conducted the performance audit from June 2011 to April 2012 in accordance with generally accepted government auditing standards.

Michael J. Sullivan, Director Acquisition and Sourcing Management, also noted in his report that, “The lessons learned on the maintenance of the stealthy F-22A may also have implications for the F-35 Joint Strike Fighter.”

Lockheed Martin announced May 2 that the 195th and final F-22 Raptor was delivered to U.S. Air Force leadership in a ceremony at the Lockheed Martin Aeronautics site in Marietta, Ga. With this delivery, the Air Force now possesses the world’s only 5th generation stealth fighter aircraft fleet in the world.

“There is no longer any nation that wishes us ill, or any adversary who wishes us harm, that has any doubt that their actions will have consequences – that they will be held to account and that our response will be undeterred,” said Robert J. Stevens, Lockheed Martin’s chairman and CEO. “The very existence of this airplane – your airplane – has altered the strategic landscape forever.”

The Air Force’s F-22A Raptor is the only operational fifth-generation tactical aircraft, incorporating a low observable (stealth) and highly maneuverable airframe, advanced integrated avionics, and a supercruise engine capable of sustained supersonic flight.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines April 23, 2014

News: U.S. conducts spy flights over Russia - After a tit-for-tat series of delays, the United States conducted an Open Skies Treaty intelligence flight over Russian territory April 21, a State Department official said.  Army paratroopers heading to Poland after Russian annexation of Crimea - U.S. Army paratroopers are arriving in Poland to begin a series of...
 
 

News Briefs April 23, 2014

U.S. military deaths in Afghanistan at 2,177 As of April 22, 2014, at least 2,177 members of the U.S. military had died in Afghanistan as a result of the U.S.-led invasion of Afghanistan in late 2001, according to an Associated Press count. The AP count is one less than the Defense Department’s tally. At least...
 
 

Northrop Grumman sets new greenhouse gas emission reduction goal of 30 percent by 2020

Northrop Grumman announced April 22 its commitment to reduce greenhouse gas emissions by 30 percent from 2010 levels by 2020, as part of its commemoration of Earth Day.   “Northrop Grumman is dedicated to top performance in environmental sustainability,” said Wes Bush, chairman, chief executive officer and president. “This new goal sets the bar significantly...
 

 

Lockheed Martin demonstrates enhanced ground control system, software for small UAV

Lockheed Martin’s Group 1 family of unmanned aircraft systems is migrating to enhanced automation capabilities using its Kestrelô “Fly Light” flight control systems and industry-leading mobile Ground Control Station software. The increased automation allows operators to focus on executing the mission, rather than flying various aircraft. Earlier this year, Lockheed MartinR...
 
 

U.S. Navy awards General Dynamics $33 million to operate, maintain military sealift ships

The U.S. Navy has awarded General Dynamics American Overseas Marine LLC a $32.7 million contract modification to operate and maintain seven large, medium-speed, roll-on / roll-off ships for the Military Sealift Command. AMSEA is a wholly owned subsidiary of General Dynamics. Under the terms of the modification, AMSEA will provide services including crewing, engineering, maintenance,...
 
 

US Navy deploys Standard Missile-3 Block IB for first time

In partnership with the Missile Defense Agency, the U.S. Navy deployed the second-generation Standard Missile-3 Block IB made by Raytheon for the first time, initiating the second phase of the Phased Adaptive Approach. “The SM-3 Block IB’s completion of initial operational testing last year set the stage for a rapid deployment to theater,” said Dr....
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>