An AFRL-developed process produces all 92 end fitting shapes with just two separate forging dies; the end fittings significantly decrease the a cracking issue in the C-5 bulkhead floor.

Newly developed structural technologies developed by the Air Force Research Laboratory have solved critical cracking issues with the C-5 cargo aircraft, thereby expanding the aircraft’s serviceability.

As part of the Durable C-5 Structural Improvements Program, AFRL recently investigated cracking issues that have been occurring in C-5 cargo floor bulkhead end fittings, part of the under-floor structure in these large cargo vehicles. The cracks, caused by stress corrosion, led to increased maintenance cost, and had the potential of reducing the amount of cargo the C-5s carry.

Traditional repair methods proved insufficient because replacement fittings would often crack during the machining process, and had a shorter lifespan than original parts. To solve the problem, researchers looked into a new, more stress corrosion-resistant aluminum alloy and a new die forging process by which all 92 fitting shapes required for the C-5 bulkhead floor could be produced using only two separate forging dies.

This new process saves money, time and effort. Additionally, the reshaped fittings created by the forging process yield an optimized design less prone to cracks. The new end fittings will provide numerous benefits for the retrofitted C-5 vehicles, including a 25 percent overall cost savings, an 80 percent reduction in fabrication time, and a 60 percent increase in service life of the fittings.

This technology has been transitioned to the Warner Robins Air Logistics Center, Ga., where the new end fittings have been installed in select C-5 aircraft. Additionally, AFRL researchers say this forging process can be applied to other aircraft that experience the same cracking issues.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines July 21, 2014

News: IDF releases Iron Dome interception rate - Israel’s Iron Dome system has successfully intercepted 86 percent of the Palestinian rockets that it has engaged during Operation ‘Protective Edge’, according to the Israel Defense Forces.   Business: The turnaround of France’s defense giant Thales - Within seconds of meeting Jean-Bernard Levy it becomes apparent that h...
 
 

News Briefs July 21, 2014

Corruption investigated in Kansas National Guard The Kansas Adjutant General’s office says federal authorities are investigating possible corruption involving outside medical companies’ contracts with the Kansas Army National Guard. Sharon Watson, spokeswoman for the adjutant general’s office, confirmed the investigation Friday to The Lawrence Journal-World but declined to rel...
 
 
Air Force photograph by Rick Goodfriend

B61 undergoes testing in AEDC wind tunnel

Air Force photograph by Rick Goodfriend Arnold Engineering Development Complex engineers recently joined researchers with Sandia National Laboratories to perform a wind tunnel test on a full-scale mock-up B61. Pictured with the...
 

 
Army photograph by Charles Kennedy

New CT scanner finds diverse, important uses for researchers

Army photograph by Charles Kennedy Turning a now-standard tool for medical diagnostics and therapeutics to a host of new applications, the U. S. Army Research Laboratory’s Survivability/Lethality Analysis Directorate rece...
 
 

Ingalls Shipbuilding awarded $23.5 million LHA 8 affordability contract

Huntington Ingalls Industries’ Ingalls Shipbuilding division has been awarded an affordability design contract for $23.5 million for early industry involvement to reduce the construction and life-cycle cost for the amphibious assault ship LHA 8. “Ingalls Shipbuilding has been constructing large-deck amphibious ships for nearly 50 years, and this contract will build on our company...
 
 
Marine Corps photograph

DOD identifies missing World War II Marine

Marine Corps photograph Marines wounded during the landing on Tarawa in November 1943 are towed out on rubber boats to larger vessels that will take them to base hospitals. The Department of Defense POW/Missing Personnel Office...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>