Teamwork leads to record-breaking achievement

Tags:
by Brandice J. O'Brien
Tinker AFB, Okla.

A banner says it all for the Oklahoma City Air Logistics Complex mechanics who produced a B-1 Bomber early and proudly delivered it to the customer this month. Maintainers on the bomber even beat their own tight goals by finishing in 129 days.

A B-1B Lancer just made history. The aircraft swept through programmed depot maintenance in record-breaking time – just 129 flow days. It was produced one day sooner than the unit’s goal and 24 days sooner than the fiscal 2012 goal.

Officials credit the achievement to teamwork, years of continuous process improvement and an emphasis on material supportability and mechanic support.

“Simply put, you are the best! I am so proud of our team for breaking records the ‘right way’ with character and integrity. This is the first B-1 produced in 129 days with only 39 days in post dock, 24 days early, and a first flight test acceptance,” said Col. Brad Tannehill, 76th Aircraft Maintenance Group commander. “I have great faith that our team will continue to achieve the impossible; we are aiming beyond what we are capable of, and are developing a complete disregard for where our abilities end. It’s not about how good we are. It is about how good we want to be. We want to be the best in the world, world class. To be the BEST we must continue to Believe, Encourage, Share and Trust our teammates. We are still not close to reaching our full potential, the ‘Art of the Possible.’”

Charles “Chuck” Alley, 565th Aircraft Maintenance Squadron acting director for B-1 Maintenance, said the unit will continue to use eight-step problem-solving methods, root cause analysis and a recent enterprise value stream analysis to further cut flow days.

“We ultimately want to get the mechanics on the floor turning the wrenches with exactly what they need to be able to do their job safely, efficiently and with the highest degree of quality possible,” he said.

Their efforts have paid off.

When a B-1 arrives at Tinker Air Force Base, Okla., for PDM it is processed through five stages, or gates – pre-dock, access and inspection, defect repair and initial hydraulic power, hydraulic power operational check and post dock, where the jet receives a functional check flight. While the squadron’s goal for an aircraft is to move through post-dock in 40 calendar days, in early 2012 Tinker averaged 56 days and three functional check flights. Now, it’s at 48 days and two functional check flights. But, this particular aircraft moved through in only 39 days and required only one functional check flight.

Prior to the 129-day aircraft, the last five B-1s had been produced in 145 days, Alley said.

“It was the first-time ever we broke the 40-day post-dock requirement,” Alley said. “This achievement speaks highly of the end product that went through the process from input through the dock gates and arrived out to the post-dock arena. It’s a phenomenal improvement over fiscal 2010, which produced an aircraft in 208 flow days.”

Within those gates, there are countless people who touch or are affiliated with the aircraft including personnel from the aircraft maintenance group and system program office, the 76th Commodities Maintenance Group, 76th Propulsion Maintenance Group, Defense Logistics Agency and 10th Flight Test Squadron pilots.

Craig Baumann, a mechanic in B-1 Avionics with the 565 AMXS B-1 Flight, has worked on these aircraft since 1997.

“This airframe is an animal. Every one of them is made out of the same blueprint, but they’re all different and the field flies them until they’re pretty worn out,” Baumann said. “But, we give them good jets back; that’s why we’re in this business.”

After achieving the turnaround time of 129 days, Baumann said it is possible to do it again.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines May 22, 2013

Business Rolls-Royce wins engine order from U.S. lessor CIT Britain’s Rolls-Royce has won a contract to supply engines to power 23 Airbus aircraft ordered by U.S. leasing company CIT Aerospace, it said May 22. Boeing defense chief sees rising R&D, margins Boeing’s defense division expects to continue growing its research and development spending and operating...
 
 

News Briefs May 22, 2013

Unclaimed veterans’ remains laid to rest in Calif. The unclaimed remains of 35 military veterans and two military wives have been given formal military burials in Northern California. The Santa Rosa Press Democrat says the remains, some left unclaimed for decades, were escorted by 120 motorcycles from Santa Rosa to the Sacramento Valley National Cemetery...
 
 

Northrop Grumman will Help U.S. Navy mature laser weapon systems, components for surface self-defense missions

REDONDO BEACH, Calif. -†The U.S. Navy has selected Northrop Grumman for the initial phase of the Solid State Laser Technology Maturation (SSL-TM) program. SSL-TM is a research and development project to mature solid-state, high-power laser weapon systems and components for ship defense. This selection is the first step in the development of a Prototype Laser...
 

 

General Dynamics to deliver U.S. Army’s newest tactical ground station intelligence system

The U.S. Army awarded a contract to General Dynamics C4 Systems for 10 vehicle-mounted Tactical Ground Station Lot D systems with an option for 11 additional systems. The TGS system is part of the Distributed Common Ground System-Army, the Army’s primary deployed system for posting, processing and distributing intelligence, surveillance and reconnaissance† information in real...
 
 

Defense Acquisition Board approves Standard Missile-6 full-rate production

A Defense Acquisition Board approved full-rate production of Raytheon’s Standard Missile-6. Once operational in 2013, the SM-6 will provide U.S. Navy vessels extended range protection against fixed- and rotary-wing aircraft, unmanned aerial vehicles and cruise missiles. “SM-6 is a game-changing, transformational fleet defense missile, and we’re on track to reach initial operating ...
 
 

United to add 40 More Embraer 76-seat aircraft to United Express fleet

United Airlines announced May 21 a capacity purchase agreement for SkyWest Airlines, Inc., a wholly-owned subsidiary of SkyWest, Inc., to operate 40 Embraer 175 aircraft under the United Express brand. SkyWest,†Inc. will purchase the 40 76-seat aircraft with deliveries in 2014 and 2015. These aircraft are in addition to 30 Embraer 175 aircraft that United...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>