Teamwork leads to record-breaking achievement

Tags:
by Brandice J. O'Brien
Tinker AFB, Okla.

A banner says it all for the Oklahoma City Air Logistics Complex mechanics who produced a B-1 Bomber early and proudly delivered it to the customer this month. Maintainers on the bomber even beat their own tight goals by finishing in 129 days.

A B-1B Lancer just made history. The aircraft swept through programmed depot maintenance in record-breaking time – just 129 flow days. It was produced one day sooner than the unit’s goal and 24 days sooner than the fiscal 2012 goal.

Officials credit the achievement to teamwork, years of continuous process improvement and an emphasis on material supportability and mechanic support.

“Simply put, you are the best! I am so proud of our team for breaking records the ‘right way’ with character and integrity. This is the first B-1 produced in 129 days with only 39 days in post dock, 24 days early, and a first flight test acceptance,” said Col. Brad Tannehill, 76th Aircraft Maintenance Group commander. “I have great faith that our team will continue to achieve the impossible; we are aiming beyond what we are capable of, and are developing a complete disregard for where our abilities end. It’s not about how good we are. It is about how good we want to be. We want to be the best in the world, world class. To be the BEST we must continue to Believe, Encourage, Share and Trust our teammates. We are still not close to reaching our full potential, the ‘Art of the Possible.'”

Charles “Chuck” Alley, 565th Aircraft Maintenance Squadron acting director for B-1 Maintenance, said the unit will continue to use eight-step problem-solving methods, root cause analysis and a recent enterprise value stream analysis to further cut flow days.

“We ultimately want to get the mechanics on the floor turning the wrenches with exactly what they need to be able to do their job safely, efficiently and with the highest degree of quality possible,” he said.

Their efforts have paid off.

When a B-1 arrives at Tinker Air Force Base, Okla., for PDM it is processed through five stages, or gates – pre-dock, access and inspection, defect repair and initial hydraulic power, hydraulic power operational check and post dock, where the jet receives a functional check flight. While the squadron’s goal for an aircraft is to move through post-dock in 40 calendar days, in early 2012 Tinker averaged 56 days and three functional check flights. Now, it’s at 48 days and two functional check flights. But, this particular aircraft moved through in only 39 days and required only one functional check flight.

Prior to the 129-day aircraft, the last five B-1s had been produced in 145 days, Alley said.

“It was the first-time ever we broke the 40-day post-dock requirement,” Alley said. “This achievement speaks highly of the end product that went through the process from input through the dock gates and arrived out to the post-dock arena. It’s a phenomenal improvement over fiscal 2010, which produced an aircraft in 208 flow days.”

Within those gates, there are countless people who touch or are affiliated with the aircraft including personnel from the aircraft maintenance group and system program office, the 76th Commodities Maintenance Group, 76th Propulsion Maintenance Group, Defense Logistics Agency and 10th Flight Test Squadron pilots.

Craig Baumann, a mechanic in B-1 Avionics with the 565 AMXS B-1 Flight, has worked on these aircraft since 1997.

“This airframe is an animal. Every one of them is made out of the same blueprint, but they’re all different and the field flies them until they’re pretty worn out,” Baumann said. “But, we give them good jets back; that’s why we’re in this business.”

After achieving the turnaround time of 129 days, Baumann said it is possible to do it again.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines December 17, 2014

News: U.S. Air Force tanker platform slated for year-end debut - Boeing is planning for first flight of its 767-2C – upon which the U.S. Air Force’s new KC-46 tanker will be based – by year’s end, six months late. Northrop Grumman wins $657.4 million deal to supply drones to South Korea - Northrop Grumman has won...
 
 

NASA launches new Micro-g NExT for undergraduates

NASA is offering undergraduate students an opportunity to participate in a new microgravity activity called Micro-g Neutral Buoyancy Experiment Design Teams. The deadline for proposals is Jan. 28, 2015. Micro-g NExT challenges students to work in teams to design and build prototypes of spacewalking tools to be used by astronauts for spacewalk training in the...
 
 
launch1

Storm fails to quench liftoff of secret reconnaissance satellite

The fiery launch of an Atlas V (541), among the most powerful of the venerable Atlas family, briefly dispelled the gloom over Californiaís Central Coast on the evening of Dec. 12. A team of personnel from United Launch Allianc...
 

 
Coast Guard photograph

Navy demonstrates unmanned helicopter operations aboard Coast Guard cutter

http://static.dvidshub.net/media/video/1412/DOD_102145893/DOD_102145893-512×288-442k.mp4 Coast Guard photograph An MQ-8B Fire Scout UAS is tested off the Coast Guard Cutter Bertholf near Los Angeles, Dec. 5 2014. The Coast...
 
 
GPS-OCX

GPS III, OCX successfully demonstrate key satellite command, control capabilities

Lockheed Martin and Raytheon successfully completed the fourth of five planned launch and early orbit exercises to demonstrate new automation capabilities, information assurance and launch readiness of the worldís most powerfu...
 
 

Aerojet Rocketdyne successfully demonstrates 3D printed rocket propulsion system for satellites

Aerojet Rocketdyne has successfully completed a hot-fire test of its MPS-120 CubeSat High-Impulse Adaptable Modular Propulsion System. The MPS-120 is the first 3D-printed hydrazine integrated propulsion system and is designed to provide propulsion for CubeSats, enabling missions not previously available to these tiny satellites. The project was funded out of the NASA Office of Chief...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>