Teamwork leads to record-breaking achievement

Tags:
by Brandice J. O'Brien
Tinker AFB, Okla.

A banner says it all for the Oklahoma City Air Logistics Complex mechanics who produced a B-1 Bomber early and proudly delivered it to the customer this month. Maintainers on the bomber even beat their own tight goals by finishing in 129 days.

A B-1B Lancer just made history. The aircraft swept through programmed depot maintenance in record-breaking time – just 129 flow days. It was produced one day sooner than the unit’s goal and 24 days sooner than the fiscal 2012 goal.

Officials credit the achievement to teamwork, years of continuous process improvement and an emphasis on material supportability and mechanic support.

“Simply put, you are the best! I am so proud of our team for breaking records the ‘right way’ with character and integrity. This is the first B-1 produced in 129 days with only 39 days in post dock, 24 days early, and a first flight test acceptance,” said Col. Brad Tannehill, 76th Aircraft Maintenance Group commander. “I have great faith that our team will continue to achieve the impossible; we are aiming beyond what we are capable of, and are developing a complete disregard for where our abilities end. It’s not about how good we are. It is about how good we want to be. We want to be the best in the world, world class. To be the BEST we must continue to Believe, Encourage, Share and Trust our teammates. We are still not close to reaching our full potential, the ‘Art of the Possible.’”

Charles “Chuck” Alley, 565th Aircraft Maintenance Squadron acting director for B-1 Maintenance, said the unit will continue to use eight-step problem-solving methods, root cause analysis and a recent enterprise value stream analysis to further cut flow days.

“We ultimately want to get the mechanics on the floor turning the wrenches with exactly what they need to be able to do their job safely, efficiently and with the highest degree of quality possible,” he said.

Their efforts have paid off.

When a B-1 arrives at Tinker Air Force Base, Okla., for PDM it is processed through five stages, or gates – pre-dock, access and inspection, defect repair and initial hydraulic power, hydraulic power operational check and post dock, where the jet receives a functional check flight. While the squadron’s goal for an aircraft is to move through post-dock in 40 calendar days, in early 2012 Tinker averaged 56 days and three functional check flights. Now, it’s at 48 days and two functional check flights. But, this particular aircraft moved through in only 39 days and required only one functional check flight.

Prior to the 129-day aircraft, the last five B-1s had been produced in 145 days, Alley said.

“It was the first-time ever we broke the 40-day post-dock requirement,” Alley said. “This achievement speaks highly of the end product that went through the process from input through the dock gates and arrived out to the post-dock arena. It’s a phenomenal improvement over fiscal 2010, which produced an aircraft in 208 flow days.”

Within those gates, there are countless people who touch or are affiliated with the aircraft including personnel from the aircraft maintenance group and system program office, the 76th Commodities Maintenance Group, 76th Propulsion Maintenance Group, Defense Logistics Agency and 10th Flight Test Squadron pilots.

Craig Baumann, a mechanic in B-1 Avionics with the 565 AMXS B-1 Flight, has worked on these aircraft since 1997.

“This airframe is an animal. Every one of them is made out of the same blueprint, but they’re all different and the field flies them until they’re pretty worn out,” Baumann said. “But, we give them good jets back; that’s why we’re in this business.”

After achieving the turnaround time of 129 days, Baumann said it is possible to do it again.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines August 28, 2014

News: After F-15 jet crash in Virginia, rescue helicopters search for pilot - Helicopters are searching for an Air National Guard pilot after his F-15 jet crashed in the mountains of Virginia this morning, military officials said.   Business: U.S. Air Force 3DELRR contract expected soon - The U.S. Air Force could award the contract for its...
 
 

News Briefs August 28, 2014

Russian directing new offensive in Ukraine The Obama administration believes Russia is leading a new military counteroffensive in Ukraine. U.S. State Department spokeswoman Jen Psaki says Russia has sent additional columns of tanks and armored vehicles into its neighbor’s territory. She says the incursions suggest a ìRussian-directed counteroffensive is likely underway in the contested e...
 
 
LM-C5

Double Deuce

A U.S. Air Force crew ferried the 22nd C-5M Super Galaxy from the Lockheed Martin facilities in Marietta, Ga., Aug. 25. Aircraft 86-0011 was ferried by a crew led by Maj. Gen. Dwyer L. Dennis, Director, Global Reach Programs, O...
 

 
Northrop Grumman photograph

First ever RQ-4 Global Hawk hits 100th flight on NASA mission

Northrop Grumman photograph A historical look at the first Global Hawk (AV1) during its maiden flight over Edwards Air Force Base, Calif., on Feb. 28, 1998. AV1 has made history again with its 100th flight in support of NASA en...
 
 

Northrop Grumman’s CIRCM system completes U.S. Army flight testing

Northrop Grumman’s Common Infrared Countermeasures system recently completed another round of U.S. Army testing by demonstrating its capabilities on a UH-60M Black Hawk helicopter. The flight test was conducted at Redstone Arsenal in Huntsville, Ala., by the Redstone Test Center. The Northrop Grumman CIRCM system was subjected to rigorous conditions over a six-week period, after...
 
 
NASA photograph by David Olive

NASA completes successful battery of tests on composite cryotank

https://www.youtube.com/embed/qkGI6JeNY0E?enablejsapi=1&rel=0 NASA photograph by David Olive One of the largest composite cryotanks ever built recently completed a battery of tests at NASA’s Marshall Space Flight Cen...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>