KC-46 enters critical design review phase

The Air Force KC-46A program director described the critical development phases of the next-generation refueling aircraft during the 2012 Air Force Association Air and Space Conference and Technology Exposition in Washington, D.C., Sept. 18.

Maj. Gen. John F. Thompson, program executive officer for Tanker Programs, Air Force Life Cycle Management Center, Wright-Patterson Air Force Base, Ohio, said that while KC-46′s preliminary aircraft design review is complete, additional steps must be taken to develop a final aircraft design that meets system requirements.

Thompson added that 18 months into the aircraft development program the KC-46A is on track for critical design review in the fourth quarter of next year.

“There is a possibility in any program to have 50 number one priorities; I have never believed in that concept,” Thompson said. “I will have a lot of number two and … number three priorities, but my number one priority … is to successfully get through the critical design review next year.”

The aircraft configuration will advance, Thompson explained, from the commercial Boeing model 767-200ER aircraft to a Boeing model 767-2C Provisioned Freighter variant before final modification into a military certified KC-46 tanker, Thompson explained.

Select design features will allow the aircraft to carry out its “multi-role capabilities,” including cargo transportation, passenger transportation and patient transportation (in addition to its primary role of aerial refueling),” Thompson added.

The KC-46 aircraft features an improved refueling system with 212,000 pounds of fuel delivery capabilities, capability to receive fuel in flight, 65,000 pounds of cargo carrying capability, passenger aero-medical capabilities, and engines each producing 62,000 pounds of thrust.

“Our goal is one program, one plan,” Thompson said. “We are actually bending metal on this aircraft — it is not just a paper design anymore.”

Currently, testing has begun for the KC-46. Testing to date includes live fire and system integration lab testing.

“From a sustainment and supportability standpoint … our goal is to go to 100 percent organically managed sustainment on this weapon system,” Thompson said.

This means the Air Force may partner with industry for certain sustainment repair activities, but will remain in the lead for management purposes.

Despite the work that still remains in the KC-46 development, 18 next-generation refuelers are scheduled to join the fleet by 2017, Thompson said, adding that a total of 179 KC-46 aircraft are slated to be delivered by 2027.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines August 18, 2014

News: U.S. mission in Iraq could expand, Pentagon official says - The mission for U.S. troops in Iraq to help Kurdish and Iraqi security forces in their fight against Islamic militants remains limited for now, but may expand after Iraqi leaders form a new government, a Pentagon spokesman said Aug. 19.   Business: Fuel deals top...
 
 

News Briefs August 20, 2014

Trials complete on fourth Coast Guard cutter Ingalls Shipbuilding in Pascagoula, Miss., has completed acceptance sea trials for the company’s fourth U.S. Coast Guard national security cutter, Hamilton. Jim French, Ingalls’ NSC program manager, tells The Mississippi Press) the Hamilton is scheduled to be delivered next month and commissioned on Dec. 6 in Charleston, South...
 
 
Army photograph by Sgt. Thomas Duval

Air Force, Army Aviation come together to complete vital mission in Egypt

Army photograph by Sgt. Thomas Duval Soldiers and airmen load a UH-60 Black Hawk into an Air Force C17 Globemaster III Aug. 19, 2104, at an old Israeli airstrip in the Sinai Peninsula of Egypt. The airstrip is now used by the M...
 

 
Air Force photograph by TSgt. Terri Praden

Joint effort validates ability to move Stryker vehicles via air

Air Force photograph by TSgt. Terri Praden An Army Stryker combat vehicle is guided into a C-17 Globemaster III during a 25th Infantry Division training exercise Aug. 13, 2014, at Joint Base Pearl Harbor-Hickam, Hawaii. The Str...
 
 
NASA image

Ozone-depleting compound persists, NASA research shows

NASA image Satellites observed the largest ozone hole over Antarctica in 2006. Purple and blue represent areas of low ozone concentrations in the atmosphere; yellow and red are areas of higher concentrations. NASA research show...
 
 

F-16V completes major capability milestone

The newest configuration of the F-16 Fighting Falcon, the F-16V, has reached a major capability milestone with the integration of a new Active Electronically Scanned Array radar. Completing this milestone on schedule demonstrates our ability to meet program commitments, said Roderick McLean, vice president and general manager of the F-16/F-22 Integrated Fighter Group at Lockheed...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>