Boeing 737 MAX achieves ‘firm concept’


Boeing has finished defining in broad terms its newest single-aisle airplane, the 737 MAX, recently completing a major milestone in development known as ‘Firm Concept’.

“The program has achieved this development milestone by defining the significant changes needed to deliver the performance we’ve committed to our customers,” said Beverly Wyse, vice president and general manager 737 program. “The team has a firm plan in place to incorporate all the changes necessary to realize a 13 percent fuel-use reduction within the scope and schedule of the program.”
Fuel-use reduction changes include new LEAP-1B engines from CFM International, a redesigned tail cone and Advanced Technology winglets. Other changes allow these fuel-saving features to be integrated into the overall airplane design.

Boeing also decided to incorporate limited systems changes to the 737 MAX. These include an electronic bleed air system that will be supplied by Honeywell and large-format displays, supplied by Rockwell Collins, for the flight deck of the 737 MAX.

“In keeping with our commitment to customers to continuously improve the 737, we also are making an investment in the future capability of the 737 MAX flight deck with the new, more advanced displays,” said Wyse.

The 737 MAX flight deck will have four new large displays with significant growth capability while maintaining a common look-and-feel with the Next-Generation 737 display formats that preserves commonality with training across the 737 family.

“With large-format displays we can offer our customers future capability in the flight deck as pilot and training needs evolve, giving the 737 MAX a competitive advantage and 737 MAX operators even greater value,” said Wyse.

The team also has defined the high-speed aerodynamic lines for the 737 MAX. Through analysis and testing conducted in high- and low-speed wind tunnels, the 737 MAX design team has further refined the geometric shape of the airplane, eliminating the need for the small bump on the nose-gear door that appeared in earlier design iterations.

“Removal of the bump demonstrates how far our design work has progressed,” said Michael Teal, chief project engineer, 737 MAX.
With Firm Concept, the factory plan for the 737 MAX also has been defined. The factory plan includes a 737 MAX transition line where the initial 737 MAX airplanes will be assembled before integrating the new airplane into the existing 737 production lines in Renton, Wash.

“The 737 MAX remains on track for first delivery in 2017,” said Teal. “Now we are focused on the finer details of the configuration and we are confident we’ll be ready to begin detailed design in mid-2013.”




All of this week's top headlines to your email every Friday.


 
 

 

Headlines March 27, 2015

News General Dynamics withdraws as T-100 prime contractor General Dynamics Information Systems and Technology has withdrawn itself as the prime contractor on the T-100, the offering for the T-X trainer replacement program based on the Alenia Aermacchi M-346 design.   Business SpaceX’s fight with U.S. Air Force called a clash of perceptions Billionaire Elon Musk’s...
 
 

News Briefs March 27, 2015

Contractor extradited from Iraq pleads guilty in bribes case A man extradited from Iraq in a military contract bribery case has pleaded guilty to three charges in an agreement with federal prosecutors. U.S. District Judge Thomas Rose has scheduled sentencing for July 1 for Metin Atilan. His attorney, Nick Gounaris, says the two sides agreed...
 
 

Ninth Boeing GPS IIF reaches orbit, sends first signals

Boeing Global Positioning System (GPS) IIF satellites are steadily replenishing the orbiting constellation, continuing to improve reliability and accuracy for users around the world. The ninth GPS IIF reached orbit about three hours, 20 minutes after launching today aboard a United Launch Alliance (ULA) Delta IV rocket from Cape Canaveral Air Force Station, Fla., and...
 

 

F-35 Lightning II costs drop, report shows

A recent account of F-35 Lightning II aircraft program costs shows decreases, the Air Force’s F-35 program executive officer told reporters in a media roundtable March 24, 2015. Lt. Gen. Christopher C. Bogdan, citing this year’s selected acquisition report on the aircraft, called the roundtable to clarify cost and performance facts. He also acknowledged the...
 
 
NG-growler2

Northrop Grumman delivers center/aft ‘shipset’ for first international EA-18G Growler

Northrop Grumman photograph Northrop Grumman mechanics perform final quality inspections on the center/aft fuselage shipset produced by the company for the first Australian EA-18G Growler. The subassembly will be delivered to B...
 
 
Navy photograph by Monica McCoy

Navy conducts production acceptance test of Tomahawk missile

Navy photograph by Monica McCoy Members of the Explosive Ordnance Disposal Technology Division team at Naval Surface Warfare Center, Indian Head prepare a Tomahawk missile for a functional ground test at the Large Motor Test Fa...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>