Boeing weld technician Richard Oramous, weld engineer Tim Livengood and weld technician Gary Bennett (left to right) observe a Self Reacting Friction Stir Weld development test weld in progress at NASA’s Michoud Assembly Facility in New Orleans in support of the SLS. Boeing and NASA on Dec. 20 completed the Preliminary Design Review for the Space Launch System core stage and avionics, validating the design of the rocket that will send humans beyond low Earth orbit to places like the moon, an asteroid and ultimately Mars.

Boeing and NASA on Dec. 20 completed the Preliminary Design Review for the Space Launch System core stage and avionics, validating the design of the rocket that will send humans beyond low Earth orbit to places like the moon, an asteroid and ultimately Mars.

The PDR is a comprehensive review that demonstrates that the design meets all system requirements within acceptable risk constraints, establishing approval for proceeding with detailed design. The first mission in 2017 will be an un-crewed loop around Earth’s moon, to be followed by a crewed mission.

“Design reuse and concurrent design and production planning helped us to quickly create a core stage preliminary design that integrates heritage and new designs, all less than a year from contract award. This is an important element of our schedule management approach,” said Jim Chilton, vice president for Boeing Exploration Launch Systems.

Boeing and NASA achieved three important milestones in the past year – System Requirements Review, Systems Design Review and now PDR. Boeing can now proceed to the Critical Design Review, the final step – expected in 2014 – that officially gives Boeing the authority to proceed into production. Boeing continues to develop production capability for the heavy-lift rocket at NASA’s Michoud Assembly Facility in New Orleans.

“We are running ahead of schedule and we will use the extra time to ensure a safe and affordable rocket,” said Frank McCall, Boeing SLS deputy program manager.

The SLS program employs a growing Boeing Space Exploration workforce in Huntsville, Ala., and New Orleans, as well as in Houston; Huntington Beach and El Segundo, Calif.; Cleveland, Ohio; and Titusville, Fla.

Boeing weld engineer Tim Livengood confirms the setup on a friction stir weld test fixture at NASA’s Michoud Assembly Facility in New Orleans in support of the SLS.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines October 20, 2014

News: Navy grounds ‘Top Guns’ - The F/A-18s needs spare parts and in too many cases they’re being taken from brand new jets. This is a risk to national security and pilots’ lives.   Business: Boeing seeks revised schedule for U.S. aerial tanker - Boeing is revising its master schedule for developing the new U.S. Air Force...
 
 

News Briefs October 20, 2014

New military medical team to help with Ebola in U.S. Defense Secretary Chuck Hagel has ordered the military to prepare and train a 30-member medical support team that could provide short-term help to civilian health professionals if there are more Ebola cases in the United States. His spokesman, Rear Adm. John Kirby, says the team...
 
 

Dragon ‘fires up’ for flight

The Air Force and NATO are undergoing a cooperative development effort to upgrade the avionics and cockpit displays of AWACS aircraft belonging to the 552nd Air Control Wing at Tinker Air Force Base, Okla., and the NATO E-3 Sentrys from Geilenkirchen, Germany. The Diminishing Manufacturing Sources Replacement of Avionics for Global Operations and Navigation, otherwise...
 

 
Boeing photographs

Boeing-built X-37B successfully completes third flight

Unmanned spacecraft concludes record-setting 674-day mission   Boeing photograph A third mission of the Boeing-built X-37B Orbital Test Vehicle was completed on Oct. 17, 2014, when it landed and was recovered at Vandenberg...
 
 

Boeing concludes commercial crew space act agreement for CST-100/Atlas V

Boeing has successfully completed the final milestone of its Commercial Crew Integrated Capability Space Act Agreement with NASA. The work and testing completed under the agreement resulted in significant maturation of Boeing’s crew transportation system, including the CST-100 spacecraft and Atlas V rocket. NASA in July approved the Critical Design Review Board milestone for Boeing’...
 
 

AF to release small business research solicitations

The Air Force Small Business Innovation Research and Small Business Technology Transfer program office is set to release its fiscal year 2015 list of topics Oct. 22, on the SBIR/STTR website.  Small businesses and research institutions with expertise to address the topics’ technology challenges are encouraged to submit proposals. During 2014, the Defense Department SBIR...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>