Boeing completes preliminary design review for Space Launch System core stage

Boeing weld technician Richard Oramous, weld engineer Tim Livengood and weld technician Gary Bennett (left to right) observe a Self Reacting Friction Stir Weld development test weld in progress at NASA’s Michoud Assembly Facility in New Orleans in support of the SLS. Boeing and NASA on Dec. 20 completed the Preliminary Design Review for the Space Launch System core stage and avionics, validating the design of the rocket that will send humans beyond low Earth orbit to places like the moon, an asteroid and ultimately Mars.

Boeing and NASA on Dec. 20 completed the Preliminary Design Review for the Space Launch System core stage and avionics, validating the design of the rocket that will send humans beyond low Earth orbit to places like the moon, an asteroid and ultimately Mars.

The PDR is a comprehensive review that demonstrates that the design meets all system requirements within acceptable risk constraints, establishing approval for proceeding with detailed design. The first mission in 2017 will be an un-crewed loop around Earth’s moon, to be followed by a crewed mission.

“Design reuse and concurrent design and production planning helped us to quickly create a core stage preliminary design that integrates heritage and new designs, all less than a year from contract award. This is an important element of our schedule management approach,” said Jim Chilton, vice president for Boeing Exploration Launch Systems.

Boeing and NASA achieved three important milestones in the past year – System Requirements Review, Systems Design Review and now PDR. Boeing can now proceed to the Critical Design Review, the final step – expected in 2014 – that officially gives Boeing the authority to proceed into production. Boeing continues to develop production capability for the heavy-lift rocket at NASA’s Michoud Assembly Facility in New Orleans.

“We are running ahead of schedule and we will use the extra time to ensure a safe and affordable rocket,” said Frank McCall, Boeing SLS deputy program manager.

The SLS program employs a growing Boeing Space Exploration workforce in Huntsville, Ala., and New Orleans, as well as in Houston; Huntington Beach and El Segundo, Calif.; Cleveland, Ohio; and Titusville, Fla.

Boeing weld engineer Tim Livengood confirms the setup on a friction stir weld test fixture at NASA’s Michoud Assembly Facility in New Orleans in support of the SLS.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines September 3, 2015

News Carter To China: US ‘Will Fly, Sail, Operate Wherever Law Allows’ Defense Secretary Ash Carter, in a speech billed as all about a new personnel approach for the Pentagon, laid out a clear line in the sand of the temporary islands the Chinese have been building. http://breakingdefense.com/2015/09/carter-to-china-us-will-fly-sail-operate-wherever-law-allows/ LRS-B details emerge: Major t...
 
 

News Briefs September 3, 2015

Soldier injured after parachute failed to deploy A soldier was injured during a U.S. Army Special Operations parachute training exercise in western Montana. Army officials at Fort Bragg, N.C., say 16 soldiers were conducting a free-fall parachute jump from two Blackhawk helicopters near Hamilton Aug. 31 when one soldier had an equipment malfunction and was...
 
 

Boeing, Jet2.com finalize order for 27 Next Generation 737-800s

Boeing and UK Leisure Airline Jet2.com have finalized an order for 27 Next Generation 737-800s, valued at approximately $2.6 billion at current list prices. Jet2.com currently operates an all-Boeing fleet of nearly 60 aircraft; however, this is the organization’s first direct Boeing order.† The aircraft will be used to take the company’s package holiday and...
 

 
boeing-emirates

Boeing, Emirates celebrate airline’s 150th 777 delivery

Boeing and Emirates Airline Sept. 3 celebrated the simultaneous delivery of three 777s — two 777-300ERs and one 777 Freighter — marking the entry of the 150th 777 into Emirates’ fleet. The delivery marks the first tim...
 
 

U.S. Air Force selects Chromalloy for F108 gas turbine engine module repairs

Chromalloy announced Sept. 2 that it has been selected by the U.S. Air Force to provide repairs on low pressure turbine modules for the F108 aircraft engine fleet, in a contract valued at up to $74 million. The one-year agreement was contracted by the Tinker Air Force Base in Oklahoma and includes four one-year options...
 
 
raytheon-colorado

Raytheon expanding in Colorado Springs

Raytheon will speed up growth of its Colorado Springs presence after signing a $700 million multi-year indefinite-delivery/indefinite-quantity contract to support operations at NORAD’s Cheyenne Mountain Complex. Under the...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>