U.K. military must do more on cost overruns

Britain’s defense ministry needs to set more realistic price and delivery forecasts for its largest equipment projects, a watchdog group said Thursday after finding cost overruns in the hundreds of millions of pounds and numerous deadlines pushed back.

The National Audit Office’s report looked at Britain’s 16 largest military equipment projects and found costs have risen 468 million pounds ($749.7 million) and delivery dates pushed back a total of 139 months over the last year. In one case, a communications system developed for use in Afghanistan has been delayed to the point that it won’t be ready until after British troops are set to withdraw from the country in 2014.

Much of the cost increase came from three projects, with one instance largely due to fuel price inflation, but the fluctuations and delays reduce the ministry’s ability to plan and manage its budget effectively, the report said. Finding ways to save money is increasingly important for the Ministry of Defense now because it has been hit hard by the British government’s pledge to cut 81 billion pounds ($129.8 billion) in public spending through 2015.

“There are early signs that the Ministry of Defense has begun to make realistic trade-offs between cost, time, technical requirements and the amount of equipment to be purchased,” the report said. “Nevertheless, the continuing variances to cost and time show the MOD needs to do consistently better.”

The report analyzed the cost, time and performance of projects including the A400M transport aircraft, the Lynx Wildcat helicopter, the Type 45 Destroyer the Typhoon aircraft and the 32 million pound Falcon communications system , which had been intended for Afghanistan.

Since their initial approval dates, costs have increased by 6.6 billion pounds and the projects have been delayed by 468 months – or nearly a third longer than expected, the Audit Office said.

While it would be unrealistic to expect the defense ministry to identify every risk at the start of complex projects, the report said the persistent problems show the Ministry of Defense “has more to learn from historic performance and, in particular, set realistic timescales, although it believes it has started to do so in some cases.”

Some costs, such as 336 million pounds of fuel price inflation affecting the cost of the Future Strategic Tanker Aircraft, are out of the defense ministry’s hands, but it nonetheless needs to learn from previous projects to make the most of the funds it has, said Amyas Morse, head of the National Audit Office.

“The Ministry of Defense faces a difficult task striking a balance between delivering the capabilities it wants and those it can afford,” Morse said. “There will always be factors over which the Department has limited control.”

Margaret Hodge, chairwoman of the parliamentary committee which oversees the Audit Office’s work, said the panel will hear from the defense ministry later in January to find out what it is doing to “finally get a grip” on costs and delays. “Uncertainties around costs make it harder for the ministry to address looming capability gaps such as in air transport and air-to-air refueling aircraft,” Hodge said.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines September 2, 2014

News: Debris yields clues that pilot never ejected - When investigators were finally able to safely enter the crash site of an F-15C “Eagle” fighter jet on the afternoon of Aug. 27, they made a grim discovery that concluded more than 30 hours of searching – the pilot never managed to eject from the aircraft.  ...
 
 

News Briefs September 2, 2014

Pentagon: Iraq operations cost $560 million so far U.S. military operations in Iraq, including airstrikes and surveillance flights, have cost about $560 million since mid-June, the Pentagon said Aug. 29. Rear Adm. John Kirby, the Pentagon press secretary, said the average daily cost has been $7.5 million. He said it began at a much lower...
 
 

Unmanned aircraft partnership reaches major milestone

A team of research students and staff from Warsaw University of Technology have successfully demonstrated the first phase of flight test and integration of unmanned aircraft platforms with an autonomous mission control system. The demonstration marks a significant milestone in a partnership between the university and Lockheed Martin that began earlier this year. This is...
 

 

Raytheon delivers first Block 2 Rolling Airframe Missiles to US Navy

Raytheon delivered the first Block 2 variant of its Rolling Airframe Missile system to the U.S. Navy as part of the company’s 2012 Low Rate Initial Production contract. RAM Block 2 is a significant performance upgrade featuring enhanced kinematics, an evolved radio frequency receiver, and an improved control system. “As today’s threats continue to evolve,...
 
 
Courtesy photograph

Two Vietnam War Soldiers, one from Civil War to receive Medal of Honor

U.S. Army graphic Retired Command Sgt. Maj. Bennie G. Adkins and former Spc. 4 Donald P. Sloat will receive the Medal of Honor for actions in Vietnam. The White House announced Aug. 26 that Retired Command Sgt. Maj. Bennie G. A...
 
 

Sparks fly as NASA pushes limits of 3-D printing technology

NASA has successfully tested the most complex rocket engine parts ever designed by the agency and printed with additive manufacturing, or 3-D printing, on a test stand at NASA’s Marshall Space Flight Center in Huntsville, Ala. NASA engineers pushed the limits of technology by designing a rocket engine injector – a highly complex part that...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>