Lockheed Martin Highlights F-35 Program Achievements for 2012

FORT WORTH, Texas, Jan. 11, 2013 – The Lockheed Martin [NYSE: LMT] F-35 Lightning II Program completed 30 aircraft deliveries and achieved significant advances in flight test highlighting a year of continued progress for 2012.

The 30 F-35 deliveries in 2012 included 11 Conventional Takeoff and Landing (CTOLs), 18 Short Takeoff/Vertical Landing (STOVL) variants, and one Carrier Variant (CV). Two of the STOVLs were the program’s first two international jets, which were delivered to the United Kingdom. All but the carrier variant, known as CF-5, were production aircraft delivered to various bases for operational purposes. CF-5 was built for flight testing and delivered to the System Development and Demonstration (SDD) program. The 30 aircraft delivered in 2012 is more than double the 13 aircraft delivered in 2011.

The 2012 flight test plan called for 988 flights and 8,458 test points by Dec. 31. For the year, the SDD program flew 1,167 flights and tallied 9,319 test points. The F-35A Flight Science test aircraft flew 291 flights and accomplished 2,573 test points. The F-35B Flight Science test aircraft accomplished 396 flights and 2,443 test points. The F-35C flew 239 flights and tallied 2,247 test points. The Mission Systems test aircraft accomplished 241 flights and 2,056 test points. The F-35B also executed 102 vertical landings.

The cumulative 2012 milestones were achieved through a combination of planned test flights and test points, along with test flights and test points added throughout the year. The flight test program is now more than one third complete in aggregate with the Air Force’s F-35A variant leading the way with 43 percent complete.

“We are completing our third year of on-plan system development performance since the F-35 Program Executive Office completed its Technical Baseline Review in 2010,” said Orlando Carvalho, Lockheed Martin F-35 program executive vice president and general manager. “We fully expect this to continue in 2013 as we begin flight test of the Block 2B mission system software which will ultimately provide the initial war-fighting capability the Marines need for their initial operational capability. This successful system development progress, a maturing production line and further operational base stand up are all strong indicators of the F-35 program’s positive trajectory.”

Other 2012 major milestones:

· U.S. Secretary of Defense Leon Panetta announced the end of probation for the F-35B STOVL, nearly one year ahead of schedule.

· The first two international F-35s were delivered to the United Kingdom.

· The first three operational F-35B STOVL fighters delivered in November marked the beginning of tactical operational training at Marine Corps Air Station Yuma, Ariz.

· 33rd Fighter Wing at Eglin Air Force Base, Fla., completed its Operational Utility Evaluation (OUE) and Air Education and Training Command (AETC) officials announced that the wing is ready for pilot training in 2013. The wing flew more than 700 sorties in 2012.

· Norway procured its first F-35 commencing the largest public procurement project in its history. The event was marked by Minister of Defence Espen Barth Eide authorizing the order for the first F-35A for the Norwegian Armed Forces.

· Luke AFB was selected for F-35A U.S. and international pilot training. The base will receive 72 aircraft for three fighter squadrons.

· Major flight test accomplishments included the first aerial weapons release for the CTOL and STOVL; the F-35A reached maximum high-angle-of-attack milestone in four flights; the first night flight and night refueling missions were accomplished and both the CTOL and STOVL completed air-start testing.

· F-35 program surpassed 5,000 flight hours.

The F-35 Lightning II is a 5th Generation fighter, combining advanced stealth with fighter speed and agility, fully fused sensor information, network-enabled operations and advanced sustainment. Lockheed Martin is developing the F-35 with its principal industrial partners, Northrop Grumman and BAE Systems.

 




All of this week's top headlines to your email every Friday.


 
 

 
NG-growler2

Northrop Grumman delivers center/aft ‘shipset’ for first international EA-18G Growler

Northrop Grumman photograph Northrop Grumman mechanics perform final quality inspections on the center/aft fuselage shipset produced by the company for the first Australian EA-18G Growler. The subassembly will be delivered to B...
 
 

Boeing, ANA finalize order for three 787-10 Dreamliners

Boeing and All Nippon Airways (ANA) today finalized an order for three 787-10 Dreamliners, valued at approximately $900 million at list prices. With this order, originally announced as a commitment in January 2015, ANA becomes Boeing’s newest 787-10 customer and first airline in Asia to operate the entire family of 787 Dreamliners. “We truly appreciate...
 
 

Poland’s MESKO, Raytheon sign second letter of intent

In a move designed to collaborate and share advanced defense technologies, Raytheon’s Missile Systems business signed a Letter of Intent with MESKO, Poland’s leading missile and ammunition manufacturer. Areas of cooperation focus on Raytheon’s solutions for the KRAB howitzer precision fires and new Polish Attack Helicopter, including offset proposals and opportunities for MESK...
 

 

Airbus Group delivers first new UH-72A Lakota for Army initial-entry trainer mission

Airbus Group March 25 delivered to the U.S. Army the first UH-72A Lakota helicopter to come off the Airbus Helicopters Inc. production line configured for the Lakota’s latest mission, as the service’s initial-entry training helicopter. The aircraft will join seven Lakotas previously in the Army inventory that have already been modified to the training configuration...
 
 
Courtesy photograph

Lockheed Martin acquires high-speed wind tunnel, plans upgrades

Courtesy photograph A RATTLRS cruise-missile inlet undergoes testing at the High Speed Wind Tunnel at Lockheed Martin Missiles and Fire Control in Grand Prairie. Lockheed Martin recently purchased the facility and plans numerou...
 
 
Lockheed Martin photograph by Andrew McMurtrie

Off they go: Three more C-130Js delivered

Lockheed Martin photograph by Andrew McMurtrie March 19, a U.S. Air Force crew took delivery of and ferried an MC-130J Commando II Special Operations tanker aircraft that is assigned to Air Force Special Operations Command’s ...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>