Boeing 737 program starts building at higher production rate

boeing-737
Boeing photograph

Boeing Mechanics load initial parts of the spars for the first airplane at the new rate into a spar-assembly machine.

Boeing has begun assembly of the first Next-Generation 737 to be built at the rate of 38 airplanes per month. Over the past two years, production of the 737 has risen more than 20 percent, from 31.5 to 38 airplanes a month. In 2014, the rate will go up again to 42 airplanes a month.

Today mechanics completed loading initial parts of the spars – internal support structures in the wings ñ into an automated spar-assembly machine. The spar is the first step in building the wings and marks the start of major manufacturing for an airplane.

“The first spar load serves as the defining moment for our latest rate break, and the 737 team did it as planned, on schedule,” said Beverly Wyse, vice president and general manager of the 737 program. “We have more hard work ahead of us, but we are well on our way to another successful production rate increase.”

Employee teams have been instrumental in reducing 737 production flow by developing and implementing innovative efficiency improvements.

The first Next-Generation 737 built at the new rate is scheduled to be delivered in the second quarter of this year.




All of this week's top headlines to your email every Friday.


 
 

 
U.S. Chamber of Commerce photograph

Boeing, Embraer to collaborate on ecoDemonstrator technology tests

U.S. Chamber of Commerce photograph Frederico Curado, president & CEO of Embraer, and Marc Allen, president of Boeing International, at the Brazil-U.S. Business Summit in Washington, D.C. The event occurred during an offici...
 
 
LM-Legion

Lockheed Martin’s Legion Pod™ takes to skies

Lockheed Martin photograph by Randy Crites Lockheed Martin’s Legion Pod recently completed its first flight test, successfully tracking multiple airborne targets while flying on an F-16 in Fort Worth, Texas. Legion Pod was in...
 
 

Raytheon wins U.S. Army contract award

Will provide R&D for ground vehicles, ground robotics The U.S. Army Contracting Command ñ Warren recently awarded Raytheon the TACOM Strategic Service Solutions indefinite delivery/indefinite quantity contract. The five-year multiple-award vehicle has a ceiling value of $634 million. The agreement covers future work on sensors, fire control systems, active protection systems, and robotics...
 

 

Lockheed Martin’s EW pod delivers proven ability to protect, control electromagnetic spectrum

Lockheed Martin is testing an electronic warfare pod in the company’s advanced anechoic chamber. The pod is designed to fit a variety of platforms, and is a self-contained electronic warfare package, encompassing an entire suite of capabilities in one unit.  Electronic warfare is the art and science of controlling the electromagnetic spectrum—from jamming enemy communications...
 
 
Northrop Grumman photograph

Northrop, Navy successfully conduct E-2D Advanced Hawkeye aerial refueling CDR

Northrop Grumman photograph An E-2C test aircraft assigned to Air Test and Evaluation Squadron (VX) 20 conducts an aerial refueling dry-plug engagement with an F/A-18. Northrop Grumman along with the U.S. Navy have successfully...
 
 

Northrop, Navy celebrate legacy of EA-6B Prowler

Northrop Grumman photograph by Edgar Mills The U.S. Navy’s last operational EA-6B Prowler, designed and built by Northrop Grumman, lifts off from Naval Air Station Whidbey Island, Wash. in a ceremonial fly-away June 27 from its long time operational base. The Navy is retiring the Prowler after nearly 45 years of service.   The U.S....
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>