U.S. probes safety testing of Boeing 787 batteries

Federal regulators let Boeing write the safety conditions for the problematic battery system in its beleaguered 787 “Dreamliner,” prescribe how to test it and carry out those tests itself, according to testimony and documents released at a hearing Tuesday.

As airlines prepare to resume flying the 787 after a three-month grounding, the National Transportation Safety Board is looking at how the Federal Aviation Administration, Boeing and the company’s subcontractors tested and approved the 787′s lithium ion batteries, and whether the government grants aircraft makers too much leeway when it comes to safety.

Batteries aboard two 787s failed less than two weeks apart in January, causing a fire aboard one plane and smoke in another. The root cause of those two incidents is still unknown.

“We are here to understand why the 787 experienced unexpected battery failures following a design program led by one of the world’s leading manufacturers and a certification process that is well respected throughout the international aviation community,” NTSB’s Chairman Deborah Hersman said at the opening of a two-day board hearing. Officials with the FAA, Boeing and Boeing subcontractors responsible for the battery system were scheduled to testify.

“We are looking for lessons learned, not just for the design and certification of the failed battery, but also for knowledge that can be applied to emerging technologies going forward,” Hersman said.

The 787, Boeing’s newest and most technologically advanced plane, is the first airliner to make extensive use of lithium-ion batteries. Since the FAA doesn’t have safety regulations for the use of lithium batteries as installed equipment in planes, Boeing proposed special safety conditions the plane should have to meet. Those were effectively the same requirements FAA ultimately set for the battery system in 2007, according to documents released at the hearing.

To save manpower, the FAA designates employees of aircraft makers to oversee the safety testing of new planes. Every item that is part of an airplane, down to its nuts and bolts, must be certified as safe before the FAA approves that type of plane as safe for flight. Boeing received FAA safety certification for the 787 in August 2011.

“In a way, the designee system is admitting the FAA doesn’t have the manpower to do what is required, and also that they may not have the expertise,” said John Goglia, a former NTSB board member and aviation safety expert.

The FAA has used designated company employees to oversee and validate some safety testing for more than two decades, a practice critics complain poses conflicts of interest. The agency significantly expanded its use of designees in recent years under pressure from manufacturers, who complained it was taking the agency too long to approve new planes because they didn’t have enough staff.

If industry had to wait for government employees to develop enough technical knowledge to assess new aviation technologies, “we would just never get any products certified,” Goglia said.

It has long been known that lithium batteries are more susceptible than conventional nickel-cadmium batteries to extreme, uncontrolled temperature increases and fires that are very difficult to extinguish. But lithium batteries weigh less, store more energy and recharge faster than conventional batteries, making them attractive to aircraft makers and their airline customers.

Boeing did some of the safety testing on the 787 battery system, but much of the testing was done by a subcontractor, Thales of France, which made the 787′s electrical system, and by battery maker GS Yuasa of Japan, according to a previously released NTSB report. The testing concluded there was no chance that short-circuiting would lead to a fire, and the odds of a smoking battery were one in every 10 million flight hours.

Instead, there were two battery failures when the entire 787 fleet had clocked less than 52,000 flight hours. The first came Jan. 7 aboard a Japan Airlines 787 parked at Boston’s Logan International Airport shortly after landing from an overseas flight. Firefighters reported two small flames and dense clouds of white smoke streaming from the battery. It was more than an hour before they declared the incident under control.

Nine days later, a smoking battery aboard an All Nippon Airways 787 led to an emergency landing in Japan. The Federal Aviation Administration ordered all U.S.-registered 787s grounded the same day, and aviation authorities in other countries swiftly followed suit.

The NTSB, which is investigating the Boston incident, hasn’t yet determined the fire’s cause and may never be able to do so. The insides of the battery were severely charred, leaving few clues for investigators.

Boeing has since developed and tested a revamped version of the battery system, with changes designed to prevent a fire or to contain one should it occur. FAA officials approved the revamped batteries last week and agreed to lift the grounding order. The company has been working furiously to install the new system on the 50 Dreamliners in service worldwide. Boeing has orders for 840 of the planes from airlines around the globe.

What the NTSB uncovers regarding the FAA’s safety certification program could have important implications for the agency’s ability to handle other technology challenges, including the transition to a new air traffic control system and the introduction of unmanned aircraft into the national airspace, said Jim Hall, a former safety board chairman.

“It’s important to know that the government has oversight capability,” Hall said. “Our aviation safety, which is unparalleled at the moment in the world, has been built on having active oversight by the FAA.”

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines September 2, 2014

News: Debris yields clues that pilot never ejected - When investigators were finally able to safely enter the crash site of an F-15C “Eagle” fighter jet on the afternoon of Aug. 27, they made a grim discovery that concluded more than 30 hours of searching – the pilot never managed to eject from the aircraft.  ...
 
 

News Briefs September 2, 2014

Pentagon: Iraq operations cost $560 million so far U.S. military operations in Iraq, including airstrikes and surveillance flights, have cost about $560 million since mid-June, the Pentagon said Aug. 29. Rear Adm. John Kirby, the Pentagon press secretary, said the average daily cost has been $7.5 million. He said it began at a much lower...
 
 

Unmanned aircraft partnership reaches major milestone

A team of research students and staff from Warsaw University of Technology have successfully demonstrated the first phase of flight test and integration of unmanned aircraft platforms with an autonomous mission control system. The demonstration marks a significant milestone in a partnership between the university and Lockheed Martin that began earlier this year. This is...
 

 

Raytheon delivers first Block 2 Rolling Airframe Missiles to US Navy

Raytheon delivered the first Block 2 variant of its Rolling Airframe Missile system to the U.S. Navy as part of the company’s 2012 Low Rate Initial Production contract. RAM Block 2 is a significant performance upgrade featuring enhanced kinematics, an evolved radio frequency receiver, and an improved control system. “As today’s threats continue to evolve,...
 
 
Courtesy photograph

Two Vietnam War Soldiers, one from Civil War to receive Medal of Honor

U.S. Army graphic Retired Command Sgt. Maj. Bennie G. Adkins and former Spc. 4 Donald P. Sloat will receive the Medal of Honor for actions in Vietnam. The White House announced Aug. 26 that Retired Command Sgt. Maj. Bennie G. A...
 
 

Sparks fly as NASA pushes limits of 3-D printing technology

NASA has successfully tested the most complex rocket engine parts ever designed by the agency and printed with additive manufacturing, or 3-D printing, on a test stand at NASA’s Marshall Space Flight Center in Huntsville, Ala. NASA engineers pushed the limits of technology by designing a rocket engine injector – a highly complex part that...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>