Defense

July 17, 2013

Large rocket test facilityís altitude capability benefits from new control system

Tags:
Raquel March
Arnold AFB, Tenn.

An Arnold Engineering Development Complex systems installation crew positions the new remote Input/Output control system cabinet for the complexís Large Rocket Motor Test Facility, or J-6, that will control liquid nitrogen and gaseous nitrogen during testing.

Large rocket testing at altitude conditions has been a common occurrence at Arnold Engineering Development Complex’s state-of-the-art Large Rocket Motor Test Facility (J-6) for almost 20 years.

When ATKÆ recently tested their CASTORÆ30XL rocket in the J-6 facility, a team of engineers had completed an upgrade of the facility’s Test Unit Support System.

The result of the upgrade was the implementation of the new J-6 Facility Control System (FCS) which controls 16 major systems needed to conduct a rocket test in the facility.

The J-6 Facility provides ground-test simulations for solid-propellant rocket motors and it is used mainly for testing of stages II and III for both Minuteman and Peacekeeper ICBMs.

“A few of the critical systems are steam, gaseous nitrogen (GN2) and liquid nitrogen (LN2),” said Mickey Gipson, an Information Technology System Development manager. “Basically, the J-6 FCS is the heart of the J-6 test facility.”

A customer benefit that FCS provides is better control of automatic facility flow and pressure of steam, GN2 and LN2. Customers like ATK and the Minuteman program will also benefit from improved system calibration and pre-operations automation.

Gipson added that customers will also experience “Improved data logging and historian features and improved human machine interface and external interfaces using open standards.”

The improved interfaces will allow interaction with different manufacturer’s equipment, using a set standard, without developing special hardware or software for each test item.

System design, software design and installation were conducted by AEDC personnel.

“The original schedule of installation and checkout required nine months but our project (team) accomplished it in six months,” said Simon Choi, the Air Force project manager for the new system. “We had experienced designers and operators who are very familiar with the J-6 test process which provided technical consistency and excellent ideas.”

J-6 is designed to test Class 1.3 or 1.1 solid-propellant rocket motors capable of up to 500,000 pounds of thrust. Measuring 26-feet in diameter by 62-feet long, the horizontally oriented test cell is capable of testing rocket motors at simulated altitudes up to 100,000 feet.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines October 20, 2014

News: Navy grounds ‘Top Guns’ - The F/A-18s needs spare parts and in too many cases they’re being taken from brand new jets. This is a risk to national security and pilots’ lives.   Business: Boeing seeks revised schedule for U.S. aerial tanker - Boeing is revising its master schedule for developing the new U.S. Air Force...
 
 

News Briefs October 20, 2014

New military medical team to help with Ebola in U.S. Defense Secretary Chuck Hagel has ordered the military to prepare and train a 30-member medical support team that could provide short-term help to civilian health professionals if there are more Ebola cases in the United States. His spokesman, Rear Adm. John Kirby, says the team...
 
 

Dragon ‘fires up’ for flight

The Air Force and NATO are undergoing a cooperative development effort to upgrade the avionics and cockpit displays of AWACS aircraft belonging to the 552nd Air Control Wing at Tinker Air Force Base, Okla., and the NATO E-3 Sentrys from Geilenkirchen, Germany. The Diminishing Manufacturing Sources Replacement of Avionics for Global Operations and Navigation, otherwise...
 

 
Boeing photographs

Boeing-built X-37B successfully completes third flight

Unmanned spacecraft concludes record-setting 674-day mission   Boeing photograph A third mission of the Boeing-built X-37B Orbital Test Vehicle was completed on Oct. 17, 2014, when it landed and was recovered at Vandenberg...
 
 

Boeing concludes commercial crew space act agreement for CST-100/Atlas V

Boeing has successfully completed the final milestone of its Commercial Crew Integrated Capability Space Act Agreement with NASA. The work and testing completed under the agreement resulted in significant maturation of Boeing’s crew transportation system, including the CST-100 spacecraft and Atlas V rocket. NASA in July approved the Critical Design Review Board milestone for Boeing’...
 
 

AF to release small business research solicitations

The Air Force Small Business Innovation Research and Small Business Technology Transfer program office is set to release its fiscal year 2015 list of topics Oct. 22, on the SBIR/STTR website.  Small businesses and research institutions with expertise to address the topics’ technology challenges are encouraged to submit proposals. During 2014, the Defense Department SBIR...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>