Tenth parachute test for NASA’s Orion adds 10,000 feet of success

A complicated, high-altitude test July 24 demonstrated NASA’s new Orion spacecraft could land safely even if one of its parachutes failed.

The 10th in a series of evaluations to check out the Orion multipurpose crew vehicle’s parachute system dropped the test capsule from a C-17 aircraft at its highest altitude yet, 35,000 feet above the Arizona desert. One of three massive main parachutes was cut away early on purpose, leaving the spacecraft to land with only two. The test at the U.S. Army’s Yuma Proving Ground was the highest-altitude test of a human spacecraft parachute since NASA’s Apollo Program.

During previous tests, a mock capsule was dropped from a height of 25,000 feet and the parachutes deployed at no higher than 22,000 feet. The extra 10,000 feet of altitude at the beginning of Wednesday’s test made the demonstration the best so far of Orion’s parachute flight and landing.

“The closer we can get to actual flight conditions, the more confidence we gain in the system,” said Chris Johnson, project manager for the Orion capsule parachute assembly system at NASA’s Johnson Space Center in Houston. “What we saw today – other than the failures we put in on purpose – is very similar to what Orion will look like coming back during Exploration Flight Test-1′s Earth entry next year.”

During its return from space, Orion’s parachute system will begin to deploy 25,000 feet above the ground.

Engineers gathered data on the effects of losing a parachute during the descent. The team already proved Orion can land with just two of its three main parachutes, but this was the first opportunity to study how one parachute pulling away in mid-flight might affect the remaining two.

“We wanted to know what would happen if a cable got hooked around a sharp edge and snapped off when the parachutes deployed,” said Stu McClung, Orion’s landing and recovery system manager at Johnson. “We don’t think that would ever happen, but if it did, would it cause other failures? We want to know everything that could possibly go wrong, so that we can fix it before it does.”

The test was part of a series of parachute tests that will enable NASA to certify Orion to carry humans into space. The system already has met the necessary requirements for Orion’s first mission, Exploration Flight Test-1 (EFT-1), in September 2014. During that flight, Orion will travel 3,600 miles into orbit then return to Earth at speeds as fast as 20,000 mph, putting the parachute system to the test again as it lands in the Pacific Ocean.

 




All of this week's top headlines to your email every Friday.


 
 

 

Headlines October 20, 2014

News: Navy grounds ‘Top Guns’ - The F/A-18s needs spare parts and in too many cases they’re being taken from brand new jets. This is a risk to national security and pilots’ lives.   Business: Boeing seeks revised schedule for U.S. aerial tanker - Boeing is revising its master schedule for developing the new U.S. Air Force...
 
 

News Briefs October 20, 2014

New military medical team to help with Ebola in U.S. Defense Secretary Chuck Hagel has ordered the military to prepare and train a 30-member medical support team that could provide short-term help to civilian health professionals if there are more Ebola cases in the United States. His spokesman, Rear Adm. John Kirby, says the team...
 
 

Dragon ‘fires up’ for flight

The Air Force and NATO are undergoing a cooperative development effort to upgrade the avionics and cockpit displays of AWACS aircraft belonging to the 552nd Air Control Wing at Tinker Air Force Base, Okla., and the NATO E-3 Sentrys from Geilenkirchen, Germany. The Diminishing Manufacturing Sources Replacement of Avionics for Global Operations and Navigation, otherwise...
 

 
Boeing photographs

Boeing-built X-37B successfully completes third flight

Unmanned spacecraft concludes record-setting 674-day mission   Boeing photograph A third mission of the Boeing-built X-37B Orbital Test Vehicle was completed on Oct. 17, 2014, when it landed and was recovered at Vandenberg...
 
 

Boeing concludes commercial crew space act agreement for CST-100/Atlas V

Boeing has successfully completed the final milestone of its Commercial Crew Integrated Capability Space Act Agreement with NASA. The work and testing completed under the agreement resulted in significant maturation of Boeing’s crew transportation system, including the CST-100 spacecraft and Atlas V rocket. NASA in July approved the Critical Design Review Board milestone for Boeing’...
 
 

AF to release small business research solicitations

The Air Force Small Business Innovation Research and Small Business Technology Transfer program office is set to release its fiscal year 2015 list of topics Oct. 22, on the SBIR/STTR website.  Small businesses and research institutions with expertise to address the topics’ technology challenges are encouraged to submit proposals. During 2014, the Defense Department SBIR...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>