Defense

September 18, 2013

KC-46 progress hinges on requirements, funding stability

A1C Alexander W. Riedel
Washington, D.C.

An Air Force official Sept. 17 announced production and high-priority upgrade plans to refresh its fleet of KC-135 Stratotankers.

In a presentation at the at the Air Force Associations 2013 Air & Space Conference & Technology Exposition, Maj. Gen. John Thompson, the Air Force program executive officer for tankers, outlined continued progress in the cargo jets design and acquisition timeline.

The tanker crews – pilots, boom operators, maintainers – are conducting about 150 sorties, refueling about 450 aircraft a day – keeping the global in global reach, global vigilance and global power, Thompson said. The KC-135s are nearly 51 years old. They are fantastic weapons systems but our operators and maiAn Air Force official Sept. 17 announced production and high-priority upgrade plans to refresh its fleet of KC-135 Stratotankers.

In a presentation at the at the Air Force Associations 2013 Air & Space Conference & Technology Exposition, Maj. Gen. John Thompson, the Air Force program executive officer for tankers, outlined continued progress in the cargo jets design and acquisition timeline.

The tanker crews – pilots, boom operators, maintainers – are conducting about 150 sorties, refueling about 450 aircraft a day – keeping the global in global reach, global vigilance and global power, Thompson said. The KC-135s are nearly 51 years old. They are fantastic weapons systems but our operators and maintainers need something new and better.

In August, Air Force officials signed off on the KC-46 weapon systems critical design review, taking ownership of the design and moving forward in the acquisitions timeline.

The closure, Thompson said, represented the culmination of component and subsystem design examinations and allowed the program to progress into its manufacturing and test phases.

Beyond the test phase, officials aim to ensure technical performance is on track with the Air Forces first freighter flight scheduled in June.

The review processes benefited from commercial and Defense Department best practices, leading to overall improvements and projected cost-savings, Thompson said.

Boeing, meanwhile, is continuing integration, verification and production of four engineering and manufacturing development aircraft to support flight testing, scheduled to begin in mid-2014. The first operational KC-46 tanker is projected to fly in early 2015 – with an expected delivery of 179 tankers by 2028, Thompson said.

As the process moves from drawing to metal, Thompson said the program hit a number of milestones this year, including the award of a training contract and base selection for the tanker in May and beginning production on the first model in late June.

Assembly of the second model aircraft began in August, putting the program on track to have four test aircraft assembled by the middle of next year.

We are 40 percent done with the development program … and most of the requirements have been met early, Thompson said. Our way forward is to continue with good execution to fully fund the test program (and) develop the monitor and sustainment strategy.

Thompson said that while there is a considerable amount of uncertainty relative to sequestration in fiscal 2014, maintaining stability and support for the program is essential to keeping the pace of the process.

Requirements and funding stability are absolutely key, the general noted. As the No. 1 modernization program, Im sure (Air Force leaders) will do what they can to protect this very critical program as we go forward.
ntainers need something new and better.

In August, Air Force officials signed off on the KC-46 weapon systems critical design review, taking ownership of the design and moving forward in the acquisitions timeline.

The closure, Thompson said, represented the culmination of component and subsystem design examinations and allowed the program to progress into its manufacturing and test phases.

Beyond the test phase, officials aim to ensure technical performance is on track with the Air Forces first freighter flight scheduled in June.

The review processes benefited from commercial and Defense Department best practices, leading to overall improvements and projected cost-savings, Thompson said.

Boeing, meanwhile, is continuing integration, verification and production of four engineering and manufacturing development aircraft to support flight testing, scheduled to begin in mid-2014. The first operational KC-46 tanker is projected to fly in early 2015 – with an expected delivery of 179 tankers by 2028, Thompson said.

As the process moves from drawing to metal, Thompson said the program hit a number of milestones this year, including the award of a training contract and base selection for the tanker in May and beginning production on the first model in late June.

Assembly of the second model aircraft began in August, putting the program on track to have four test aircraft assembled by the middle of next year.

We are 40 percent done with the development program … and most of the requirements have been met early, Thompson said. Our way forward is to continue with good execution to fully fund the test program (and) develop the monitor and sustainment strategy.

Thompson said that while there is a considerable amount of uncertainty relative to sequestration in fiscal 2014, maintaining stability and support for the program is essential to keeping the pace of the process.

Requirements and funding stability are absolutely key, the general noted. As the No. 1 modernization program, Im sure (Air Force leaders) will do what they can to protect this very critical program as we go forward.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines September 3, 2015

News Carter To China: US ‘Will Fly, Sail, Operate Wherever Law Allows’ Defense Secretary Ash Carter, in a speech billed as all about a new personnel approach for the Pentagon, laid out a clear line in the sand of the temporary islands the Chinese have been building. http://breakingdefense.com/2015/09/carter-to-china-us-will-fly-sail-operate-wherever-law-allows/ LRS-B details emerge: Major t...
 
 

News Briefs September 3, 2015

Soldier injured after parachute failed to deploy A soldier was injured during a U.S. Army Special Operations parachute training exercise in western Montana. Army officials at Fort Bragg, N.C., say 16 soldiers were conducting a free-fall parachute jump from two Blackhawk helicopters near Hamilton Aug. 31 when one soldier had an equipment malfunction and was...
 
 

Boeing, Jet2.com finalize order for 27 Next Generation 737-800s

Boeing and UK Leisure Airline Jet2.com have finalized an order for 27 Next Generation 737-800s, valued at approximately $2.6 billion at current list prices. Jet2.com currently operates an all-Boeing fleet of nearly 60 aircraft; however, this is the organization’s first direct Boeing order.† The aircraft will be used to take the company’s package holiday and...
 

 
boeing-emirates

Boeing, Emirates celebrate airline’s 150th 777 delivery

Boeing and Emirates Airline Sept. 3 celebrated the simultaneous delivery of three 777s — two 777-300ERs and one 777 Freighter — marking the entry of the 150th 777 into Emirates’ fleet. The delivery marks the first tim...
 
 

U.S. Air Force selects Chromalloy for F108 gas turbine engine module repairs

Chromalloy announced Sept. 2 that it has been selected by the U.S. Air Force to provide repairs on low pressure turbine modules for the F108 aircraft engine fleet, in a contract valued at up to $74 million. The one-year agreement was contracted by the Tinker Air Force Base in Oklahoma and includes four one-year options...
 
 
raytheon-colorado

Raytheon expanding in Colorado Springs

Raytheon will speed up growth of its Colorado Springs presence after signing a $700 million multi-year indefinite-delivery/indefinite-quantity contract to support operations at NORAD’s Cheyenne Mountain Complex. Under the...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>