NASA’s Orion Spacecraft powers through first integrated system testing

Engineers in the Operations and Checkout Building at NASA’s Kennedy Space Center in Florida, perform avionics testing on the Orion spacecraft being prepared for its first trip to space later this year.

NASA’s Orion spacecraft has proven its mettle in a test designed to determine the spacecraft’s readiness for its first flight test – Exploration Flight Test-1 – later this year. EFT-1 will send the spacecraft more than 3,600 miles from Earth and return it safely.

The spacecraft ran for 26 uninterrupted hours during the final phase of a major test series completed April 8 at the agency’s Kennedy Space Center in Florida. The test verified the crew module can route power and send commands that enable the spacecraft to manage its computer system, software and data loads, propulsion valves, temperature sensors and other instrumentation.

“This has been the most significant integrated testing of the Orion spacecraft yet,” said William Gerstenmaier, associate administrator for NASA’s human exploration and operations at the agency’s Headquarters in Washington. “The work done to test the avionics with the crew module isn’t just preparing us for Orion’s first trip to space in a few months. It’s also getting us ready to send crews far into the solar system.”

In October 2013, NASA and Lockheed Martin engineers powered on Orion’s main computer for the first time. Since then, they have installed harnessing, wiring and electronics. This was the first time engineers ran the crew module through its paces to verify all system actuators respond correctly to commands and all sensors report back as planned. More than 20 miles of wire are required to connect the different systems being powered.

“Getting all the wiring right, integrating every element of the avionics together, and then testing it continuously for this many hours is a big step toward getting to deep space destinations,” said Mark Geyer, Orion program manager.

Engineers now are preparing the crew module for vibration testing, scheduled for the week of April 14. In May, the heat shield will be installed and, shortly thereafter, the crew module will be attached with the service module.

During EFT-1, an uncrewed Orion spacecraft will take a four-hour trip into space, traveling 15 times farther from Earth than the International Space Station. During its reentry into Earth’s atmosphere, Orion will be traveling at 20,000 mph, faster than any current spacecraft capable of carrying humans, and endure temperatures of approximately 4,000 degrees Fahrenheit. The data gathered during the flight will inform design decisions to improve the spacecraft that will one day carry humans to an asteroid and eventually Mars. EFT-1 is targeted for launch in December.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines April 24, 2015

News: More than $1 billion in U.S. emergency reconstruction aid goes missing in Afghanistan - A total of $1.3 billion that the Pentagon shipped to its force commanders in Afghanistan between 2004 and 2014 for the most critical reconstruction projects can’t be accounted for by the Defense Department, 60 percent of all such spending under an...
 
 

News Briefs April 24, 2015

German defense minister: widely used rifle has no future A widely used assault rifle has “no future” with the German military in its current form, Germany’s defense minister said April 22, escalating a dispute over the weapon’s alleged shortcomings. Ursula von der Leyen said last month that a study showed the G36 rifle has a...
 
 
Army photograph

Composites key to tougher, lighter armaments

Army photograph XM-360 test firing at Aberdeen Proving Ground, Md., in 2007, is shown. The Army is on the cusp of revolutionizing materials that go into armament construction, making for stronger, lighter and more durable weapo...
 

 

Northrop Grumman signs long-term agreement with Raytheon

Northrop Grumman has entered a long-term agreement with Raytheon to supply its LN-200 Inertial Measurement Unit for Raytheon optical targeting systems. The long-term agreement with Raytheon’s Space and Airborne Systems business extends through 2018. The LN-200 provides camera stabilization on optical targeting systems that conduct long-range surveillance and target acquisition for various...
 
 

NTTR supports first F-35B integration into USMC’s weapons school exercise

The Nevada Test and Training Range was part of history April 21, when four U.S. Marine Corps-assigned F-35B Lightning IIs participated in its first Marine Corps’ Final Exercise of the Weapons and Tactics Instructor course on the NTTR’s ranges. The Final Exercise, or FINEX, is the capstone event to the U.S. Marine Corps Marine Aviation...
 
 
AAR-Textron

AAR awarded new contract from Bell Helicopter Textron to support T64 engines

AAR announced April 22 that Bell Helicopter Textron Inc. awarded its Defense Systems & Logistics business unit a contract providing warehouse and logistics services in support of upgrading T64 engines for the Bell V-280 Val...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>