April 14, 2014

NASA’s Orion Spacecraft powers through first integrated system testing

Engineers in the Operations and Checkout Building at NASA’s Kennedy Space Center in Florida, perform avionics testing on the Orion spacecraft being prepared for its first trip to space later this year.

NASA’s Orion spacecraft has proven its mettle in a test designed to determine the spacecraft’s readiness for its first flight test – Exploration Flight Test-1 – later this year. EFT-1 will send the spacecraft more than 3,600 miles from Earth and return it safely.

The spacecraft ran for 26 uninterrupted hours during the final phase of a major test series completed April 8 at the agency’s Kennedy Space Center in Florida. The test verified the crew module can route power and send commands that enable the spacecraft to manage its computer system, software and data loads, propulsion valves, temperature sensors and other instrumentation.

“This has been the most significant integrated testing of the Orion spacecraft yet,” said William Gerstenmaier, associate administrator for NASA’s human exploration and operations at the agency’s Headquarters in Washington. “The work done to test the avionics with the crew module isn’t just preparing us for Orion’s first trip to space in a few months. It’s also getting us ready to send crews far into the solar system.”

In October 2013, NASA and Lockheed Martin engineers powered on Orion’s main computer for the first time. Since then, they have installed harnessing, wiring and electronics. This was the first time engineers ran the crew module through its paces to verify all system actuators respond correctly to commands and all sensors report back as planned. More than 20 miles of wire are required to connect the different systems being powered.

“Getting all the wiring right, integrating every element of the avionics together, and then testing it continuously for this many hours is a big step toward getting to deep space destinations,” said Mark Geyer, Orion program manager.

Engineers now are preparing the crew module for vibration testing, scheduled for the week of April 14. In May, the heat shield will be installed and, shortly thereafter, the crew module will be attached with the service module.

During EFT-1, an uncrewed Orion spacecraft will take a four-hour trip into space, traveling 15 times farther from Earth than the International Space Station. During its reentry into Earth’s atmosphere, Orion will be traveling at 20,000 mph, faster than any current spacecraft capable of carrying humans, and endure temperatures of approximately 4,000 degrees Fahrenheit. The data gathered during the flight will inform design decisions to improve the spacecraft that will one day carry humans to an asteroid and eventually Mars. EFT-1 is targeted for launch in December.




All of this week's top headlines to your email every Friday.


 
 

 

Headlines September 29, 2014

News: U.S. military limits warplanes used for Islamic State bombings - The U.S. is relying mostly on warplanes already positioned in the region for its air war against the Islamic State, as opposed to dispatching a major buildup of aerial forces that happened in previous campaigns.   Business: At DOD, it’s use-it-or-lose-it season - As fiscal 2014...
 
 

News Briefs September 29, 2014

Navy awards ship design grant to UNO The University of New Orleans has received a $210,000 grant from the Navy s Office of Naval Research to test information gathering and analysis techniques intended to improve warship design. The goal for warship designers is to produce a vessel that can be repurposed numerous times throughout its...
 
 
Courtesy photograph

TACP-M ties it all together

Air National Guard photograph by SSgt. Lealan Buehrer Tactical air control party specialists with the 169th Air Support Operations Squadron survey an enemy-controlled landing zone before calling in close-air support Aug. 14, 20...
 

 
Air Force photograph by A1C Thomas Spangler

Nellis aggressor squadron inactivated

Air Force photograph by A1C Thomas Spangler SSgt. Justin White signals to Maj. Sam Joplin to begin taxiing a 65th Aggressor Squadron F-15 Eagle to the runway Sept. 18, 2014, at Nellis Air Force Base Nev. The roles and responsib...
 
 
Army photograph by SSgt. Mary S. Katzenberger

82nd Airborne helps commemorate 70th Anniversary of Operation Market Garden

Army photograph by SSgt. Mary S. Katzenberger A paratrooper assigned to the 82nd Airborne Division, reflects near the grave of a British paratrooper at the Arnhem Oosterbeek War Cemetery, Sept. 14, 2014, in the Netherlands. The...
 
 

Raytheon awarded $251 million Tomahawk missile contract

The U.S. Navy has awarded Raytheon a $251 million contract to procure Tomahawk Block IV tactical cruise missiles for fiscal year 2014 with an option for 2015. The contract calls for Raytheon to build and deliver Tomahawk Block IV cruise missiles to the U.S. Navy and U.K. Royal Navy. Raytheon will also conduct flight tests...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>