Orion in final assembly at Kennedy Space Center

Lockheed Martin and NASA engineers have started the process of installing the largest heat shield ever built onto the Orion spacecraft’s crew module.

The heat shield installation marks one of the final steps in the spacecraft’s assembly leading up to its first test flight, Exploration Flight Test-1 (EFT-1), later this year.

EFT-1 will provide engineers data about the heat shield’s ability to protect the crew module from the extreme 4000-degree heat of reentry and an ocean splashdown following Orion’s 20,000 mph reentry from space. In addition, key systems such as avionics, separation events, attitude control and guidance, parachute deployment, and ground operations will be evaluated. Comprehensive data from the test flight will influence design decisions most critical to crew safety to lower risks and safely carry humans on future missions to deep space.

The team remains on schedule to complete the following milestones for the Dec. 4, 2014 launch date:

  • The crew module and service module will mate together and will undergo functional testing
  • The backshell tiles and forward bay cover will be installed onto the crew module
  • The crew module and service module will mate to the Delta IV Heavy second stage adapter
  • The spacecraft will be fueled and serviced at the Kennedy Space Center Payload Hazardous Servicing Facility
  • The launch abort system will be stacked on top of the spacecraft
  • The spacecraft will be prepped and transported to Launch Pad 37 where Lockheed Martin and United Launch Alliance will perform pad integration and launch operations

“This team has done a great job keeping us on track for Orion’s first test flight,” said Cleon Lacefield, Lockheed Martin vice president and Orion program manager. “That’s no easy task when you’re designing and building a unique vehicle for human exploration of deep space.”




All of this week's top headlines to your email every Friday.


 
 

 

Headlines July 30, 2014

News: Software to power F-35 running as much as 14 months late¬†- Software needed to operate Lockheed Martin’s F-35 jet, the Pentagon’s costliest weapons system, may be as much as 14 months late for required flight testing, according to a Pentagon review.   Business: Lockheed will turn on JLTV production line In August; 6-D truck...
 
 

News Briefs July 30, 2014

U.S. military deaths in Afghanistan at 2,197 As of July 29, 2014, at least 2,197 members of the U.S. military had died in Afghanistan as a result of the U.S.-led invasion of Afghanistan in late 2001, according to an Associated Press count. At least 1,819 military service members have died in Afghanistan as a result...
 
 
Lockheed Martin photograph by Tom Reynolds

F-35B successfully completes wet runway, crosswind testing

Lockheed Martin photograph by Tom Reynolds F-35B aircraft BF-4, piloted by Lockheed Martin Test Pilot Dan Levin, starts down the runway as part of wet runway and crosswind testing at Edwards AFB, Calif. In an important program ...
 

 
boeing-chinook

Boeing delivers first U.S. Army multiyear II configured Chinook

Boeing July 29 delivered the first multiyear II configured CH-47F Chinook helicopter to the U.S. Army one month ahead of schedule. The delivery was celebrated in a ceremony at the production facility in Ridley Township, Penn. ‚...
 
 
Army photograph by SSgt. Angela Stafford

Engineers developing safer, more accurate tracer round

Army photograph Tracer rounds enable the shooter to follow the projectile trajectory to make aiming corrections. However, the light emitted by these rounds also gives away the position of the shooter. Engineers at Picatinny Ars...
 
 
NASA photograph by Carla Thomas

Katherine Lott awarded NASA Armstrong employee scholarship

NASA photograph by Carla Thomas Katherine Lott, the recipient of the 2014 NASA Armstrong Employee Exchange Council Joseph R. Vensel Memorial Scholarship, is congratulated by NASA Armstrong center director David McBride. Flankin...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>