May 21, 2014

Orion in final assembly at Kennedy Space Center

Lockheed Martin and NASA engineers have started the process of installing the largest heat shield ever built onto the Orion spacecraft’s crew module.

The heat shield installation marks one of the final steps in the spacecraft’s assembly leading up to its first test flight, Exploration Flight Test-1 (EFT-1), later this year.

EFT-1 will provide engineers data about the heat shield’s ability to protect the crew module from the extreme 4000-degree heat of reentry and an ocean splashdown following Orion’s 20,000 mph reentry from space. In addition, key systems such as avionics, separation events, attitude control and guidance, parachute deployment, and ground operations will be evaluated. Comprehensive data from the test flight will influence design decisions most critical to crew safety to lower risks and safely carry humans on future missions to deep space.

The team remains on schedule to complete the following milestones for the Dec. 4, 2014 launch date:

  • The crew module and service module will mate together and will undergo functional testing
  • The backshell tiles and forward bay cover will be installed onto the crew module
  • The crew module and service module will mate to the Delta IV Heavy second stage adapter
  • The spacecraft will be fueled and serviced at the Kennedy Space Center Payload Hazardous Servicing Facility
  • The launch abort system will be stacked on top of the spacecraft
  • The spacecraft will be prepped and transported to Launch Pad 37 where Lockheed Martin and United Launch Alliance will perform pad integration and launch operations

“This team has done a great job keeping us on track for Orion’s first test flight,” said Cleon Lacefield, Lockheed Martin vice president and Orion program manager. “That’s no easy task when you’re designing and building a unique vehicle for human exploration of deep space.”




All of this week's top headlines to your email every Friday.


 
 

 

Headlines May 4, 2015

News: Authorization Bill a prelude to U.S. spending showdown - The House Armed Services Committee handed the Pentagon and U.S. defense sector a victory by surgically protecting weapon programs and authorizing extra war funding – but a showdown with the White House looms.   Business: Canada plans major sub-life extension - Canada has begun work on a...
 
 

New’s Briefs May 4, 2015

Senator proposes extended military foreclosure protection Sen. Sheldon Whitehouse says he has introduced legislation to help protect military service members from losing their homes to foreclosure. The Rhode Island Democrat said May 2 he has introduced a bill to extend one that is due to expire this year. The law protects service members for a...
 
 
Northrop Grumman photograph

Global Hawk earns unprecedented third consecutive sustainment award

Northrop Grumman photograph A U.S. Air Force RQ-4 Global Hawk on a runway in Palmdale, Calif. For an unprecedented third year in a row, the U.S. Air Force RQ-4 Global Hawk unmanned aircraft program was officially awarded the Dr...
 

 
Lockheed Martin photograph

Most advanced GPS satellite comes together

Lockheed Martin photograph Lockheed Martin recently fully integrated the U.S. Air Force’s first next generation GPS III satellite at the company’s Denver-area satellite manufacturing facility.  The first in a design block ...
 
 
navair-fire-scout

MQ-8C Fire Scout completes developmental flight test

Northrop Grumman photograph An MQ-8C Fire Scout†conducts its†final†developmental test flight April 29 from Naval Base Ventura County at Point Mugu, Calif.† Since its first flight in October 2013, the Navy’s new, l...
 
 
boeing-swiss

Boeing, SWISS finalize order for three additional 777-300ERs

Boeing, the Lufthansa Group and Swiss International Air Lines have finalized an order for three additional 777-300ER (Extended Range) airplanes, valued at $990 million at current list prices. This order, previously attributed t...
 




0 Comments


Be the first to comment!


Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>