Mobilization of Contractor to Site and installation of site fencing: Dec. 17 – 21, 2012
Initial surface clearance and digital geophysical survey of site: Dec. 24, 2012 – Jan. 31, 2013
Investigation of anomalies and soil sampling: Feb. 1 – 28, 2013
Evaluate data to determine need for further action: March 1, 2013
Note: All removed soils will be processed in the adjacent lay down area across North Loop Road from December 2012 to August 2013.
Project Management Responsibility
Government:
IMCOM – Army Environmental Command
IMCOM - USAG Irwin DPW Environmental Division
U.S. Army Corps of Engineers – Sacramento District
CA Department of Toxic Substances Control
CA Lahontan Regional Water Quality Control Board
Contractor:
PIKA Pirnie Joint Venture, LLC